Outline

  • Stave Loading Tooling, 19-1 RD53a L1 Stave – .zip - 11 March 2022.zip
  • Stave Loading Tooling, 19-1 RD53a L0 Stave
  • Ring Loading Tooling, 19-1 RD53a
  • Handling Frame, 19-1 RD53a L1 Stave
  • Shipping Box, 19-1 RD53a L1 Stave


Stave Loading Tooling, 19-1 L1 Stave

Version 2, revised, Stave Loading Tooling drawing drafts (not released):

.zip of all drawings and .step files - 11 March 2022.zip



ItemsVendorDateResponse
  • REF-000203575 (BASEPLATE AND PINS, LOADING FIXTURE)
  • REF-000205158 (PICK UP TABLE, RD53a QUAD)
  • REF-000202289 (LOADING BRIDGE)
Parametric USA3/7/2022

Quote: PQ104809.pdf

$8k, 4-5 week lead

Ordered 3/29/2022


Loading Tooling, L1 Stave:

Section view:


Summary of requirements for loading 19-1 Outer Barrel Stave:

  • Load RD53a Quad modules (drawings: 150um, 400um) with connectors oriented as shown in picture above
  • Load modules onto 19-1 L1 Stave (no drawing yet, preliminary CAD on LBL Windchill site)
  • Load without collisions: 200um nominal gap / 100 micron minimum gap between modules (no assembly drawing yet showing modules on stave)
  • Glue layer thickness to be 100um -50/+100um
  • ESD protection during loading: grounding of tooling
  • Mechanical protection of wire bonds during loading: stay clear of wire bonds, handle modules using tooling only, consider covers/shields
  • Baseplate to be installed onto glue robot: weight limit 7kg (per manual)
  • Stave to be removed from baseplate and transferred to test box for QC testing

Summary of specifications:

  • Closely toleranced pins/bushings – same approach as used for 19-0 tooling
    • Requirement: +/-75um module position tolerance in local support coordinate system (per requirements document "ITk Pixel Module Loading Accuracy Requirements" AT2-IP-ES-006-v3)
    • Distribute tolerances:
      • +/-50um module position relative to loading tooling baseplate coordinate system (to avoid collisions with 100um gap between modules).
        • Dowel pins in baseplate – two per module location.
        • Bridge to have bushing and slot for precision fit onto dowel pins.
      • +/-25um local support position relative to loading tooling baseplate coordinate system (to accurately place modules to meet +/-75um requirement).
        • Dowel pin in baseplate – to accurately locate one end of the Stave in Z.
        • Tooling to fasten to mounting features on ends of Stave.
  • Glue with beads to control glue layer thickness
    • 100um dia beads, for ~75um glue layer thickness on carbon fiber.
    • Loading tooling does NOT control the glue layer thickness.
      • Loading bridge to rest on the module's pickup areas (vacuum pad locations) during gluing.
      • Loading bridge to have micrometer adjusters to level the tool relative to the baseplate – to apply pressure at all vacuum pad locations during gluing.
      • Loading bridge to have micrometer adjusters to level the tool relative to the pickup table – to make good contact between vacuum pads and module.
  • Vacuum pads to pick up modules
    • Vacuum pads to fit within clear areas on modules.
    • Height adjustment of vacuum pads while on pickup table.
    • Vacuum to securely hold modules.
  • Tolerances:

Dimensioning scheme changed to hole-to-hole tolerancing (instead of hole-to-edge): 

Tolerance ItemWhere UsedTolerance (mm, Dia.)
Pick-up Table Edge RepeatabilityLocating Module to Pickup Table (repeatability of lining up module to machined edges)0.025
Pickup Table Bushing IDLocating Loading Bridge to Pick-up Table0.019
Bridge Pin ODLocating Loading Bridge to Pick-up Table0.015
Baseplate Hole ID Locating Loading Bridge to Loading Fixture0.025
Bridge Pin ODLocating Loading Bridge to Loading Fixture0.015
Baseplate Hole LocationLocating Loading Bridge to Loading Fixture (hole locations dimensioned as +/-.04 from adjacent hole, i.e. up to -.02 per hole)0.020

Total:

.119mm   (+/-.060mm)


Root Sum Square:.050mm   (+/-.025mm)

Stave position relative to loading tooling baseplate:

Tolerance ItemWhere UsedTolerance (mm, Dia.)
 Pin LocationLocating Loading Bridge to Loading Fixture (hole locations dimensioned as +/-.04 from adjacent hole, i.e. up to -.02 per hole)0.020

Pick-up Table Edge Accuracy

(absolute position)

Locating Module to Pick-up Table

*this item affects all modules equally so does not affect gap/distance between modules

0.060

Total:0.080mm (+/-.040mm)

Root Sum Square:0.063mm (+/-.032mm)
  • Total for all:
    • Limit: +/-.100mm
    • Root sum square: +/-.040mm
    • Requirement: +/-.150mm
  • Module Nominal Spacing (for 19-1 L1 Stave): .250mm (nominal gap)
    • Worst case clearance: 0.012mm
    • Clearance with RSS tolerance (3σ): 0.180mm


A design/drawings were made in 2020 (Version 1, deprecated, not released):

    • Changes for V2: add 2nd set of adjusters, stepped pins, adjustable vacuum pads, handles.


Some past presentations:


Module and Stave dimensions

Compare:

  • Module width (ensure all fit on Stave)
  • Module FE chip dimensions (re-use tooling)
ModuleFE Chips Dimensions (mm)Width (mm)Reference
RD53a Quad 150um42.137 x 40.33541.1
ITkPixV1 150um42.2 x 40.341.1
ITkPixV1 100um42.2 x 40.340.7
RD53a Linear Triplet
61.29


Can load up to 11 (of 12) modules onto 19-1 Stave prototype:

  • Stave length (flat region): 491.6mm
  • RD53a (19-1)
    • Modules length: 12*(41.1mm+.2mm)=495.6mm
    • 12 modules would result in 4mm overhang beyond end of stave. Plan not to load full stave anyway due to module availability.

  • ITkPixV1 100um
    • Modules length: 12*(40.7mm+.2mm)=490.8mm
    • Appears to fit onto Stave. Module pitch (40.9mm) different from 19-1 pitch (41.3mm) so would need to make a new baseplate with this pitch.
  • RD53a Triplet (19-1)
    • Modules length: 8*(61.29mm+.15mm)=491.52mm
    • Appears to fit onto Stave.


Stave Loading Tooling, 19-1 IB Stave

Requirements - see L1 Stave requirements above.

Summary of different requirements for loading 19-1 Inner Barrel Stave:

  • Load Triplet modules (drawing, .step)
  • Load onto 19-1 IB Stave (no drawing yet, preliminary CAD on LBL Windchill site)
  • Load without collisions: 200um nominal gap / 100 micron minimum gap between modules (no assembly drawing yet showing modules on stave)

Design concept: modify design of 19-1 L1 Stave tooling to match Triplet dimensions and pickup areas



Ring Loading Tooling

Ring loading glue locations drawing (not released): REF-000160474 (LOADING FIXTURE, 19-1 RING).pdf

Ring Loading Tooling Drawings and .step files:

  • 19-1 Ring.zip
  • In the future, plan to review drawings in Mechanics meeting and release/add to Windchill CAD library, to reduce risk of interface issues.


Handling Frame and Shipping Box

Drawings (not released):  REF-000202479 (SHIPPING AND STORAGE FIXTURE, L1 STAVE, 19-1) CHECKPRINT 14FEB2022.zip

Handling Frame with 19-1 L1 Stave:


Interface block to join Stave and Handling Frame (drawing not released):


Shipping Box:





  • No labels