Prepare
- Verify power off. (MPOD panel or IoC panel)
- Install detector in Marietta.
- Connect chiller, start flow.
- Connect data fiber.
- Connect gas line if applicable, start flow at 5l/m.
Power
- Set known values on mpod.
- Pin out cable according to diagram.
- Turn off mpod.
- Connect power cable to detector.
- Set operating voltages on mpod.
- Start DAQ and configure to begin idle.
Stabilize for 15 minutes
Record Voltage/Current/Temperature Values
Measure Pedestals (run charge injection script)
Collect Fluorescence Data
- Silver: 8-10cm distance, 35/50
Direct Illumination w/Mini-X
Process Data
Update Traveller