Kai is asking engineers to refer to a facility not supporting the upgrades in CDR 11.2 not as "FES Base" but rather "FES minus explicitly designed upgrades" ("FES -EDU")
Cavern space looks very constrained when considering beam delivery, dumping and access.
Mikael has a request to consider what the impact would be of living in FES -EDU world.
Requirements transcription into Jama - needing help
Engineers are working from one incomplete slide deck to figure out requirements - slide deck had a configuration (inadvertently?) deleted back in September.
As a consequence, Brice was surprised to learn that we might want a dual target for some experiments (e.g. ion heating target)
Considering a different mirror to put MEC below floor at final FEH location. Discussed this morning
Very preliminary discussion
Action items
Type your task here, using "@" to assign to a user and "//" to select a due dateLuke B. Fletcher to make first pass of requirements for multi-target capability in ion heating, plus requirements of flagships 4a and 4b in Jama