Documents for Type-I services construction are gathered in this page:
Image RemovedImage Added

Bundle Production

The production table can be found HERE.

 Below is the pre-production table.

Pre-production

Serial Number

Date produced Shipped 

Length Stave

DCS Type

Staves Length

Comments

Q/A Traveller

IBL-TypeI-03

15 June 2013

Long

Humidity

n/a

Pre-production

 

AXON

DCS

L Potting

L AXON
(head)

L Data

Comments

Pre-Production   

IBL-TypeI-04

30 June 2013

Long

Humidity

n/a

        

IBL-TypeI-01

April 2013

 

 

 

  

n/a

  

n/a

 

 

 

 

Electrical cable

IBL-TypeI-02

01 June 2013

 

 

 

  

Long

  

Humidity

 

 

 

Pre-production at CERN, substitute power connector

IBL-TypeI-03

15 June 2013

 

 

 

 

  

Long

 

...

Material Part Number  

Humidity

 

 

Needed

In hands

Comments

Potting ferrule

n/a

80

100

 

Connector Board

n/a

40

50

 

ConnB Shells

n/a

40

8

 

ConnB Shell Nuts

 

80

 

 

ConnB Square Nuts

n/a

40

41

 

ConnB Ferrule

n/a

40

45

 

Cable Board

n/a

40

50

 

CB NTC

 

40

100

 

Cooling Pipe NTC

 

20

100

 

PP1 NTC

 

20

100

 

CB Humidity

 

20

84

 

Data bundle Braid

 

 

 

 

Data bundle Kevlar

 

 

 

 

Shrink tube

40x2x4cm=320cm

 

 

Data AWG36 wires

17 rolls (1000 feet)

29

 

Data AWG28 wires

15 rolls (1000 feet)

14

 

Pre-production at CERN, substitute power connector

IBL-TypeI-04

30 June 2013

 

 

Long

 

Humidity

 

 

 

Pre-production at CERN, substitute power connector

IBL-TypeI-05

23 July 2013

 

 

Long

 

Humidity

 

 

 

Pre-production , substitute power connector

IBL-TypeI-06

19 August 2013

05

02

Long

 

Humidity

2460

3487

4960

Bad AXON Connector.

IBL-TypeI-07

10 Oct. 2013

05

02

Long

003

Humidity

2458

3483

4946

AWG22 Wires for LV.

Q/A Documents:

BareWireResistance.xlsx
LV_drop.xlsx
Touch-1 Resistance Measurements
Data Transmissions LogFiles

Documentations:

Type-I-QA-20141102.docx    [Touch1 pictures: 1, 2, 3, 4, 5, 6, 7 ]
distance_IPT_12June.jpg   ATUIBLP_0034_12June.pdf   ATUIBLP_0070_12June.pdf
Type1_assembly_

...

V7.docx

...

  [V6] [V5, Comments] [V4]  [V3]
Type1 Potting Procedure
IBLType1Cable.ver6.pdf [V5->V6 change]  [V5 ]
Type-1 assembly_3.docx
IBLType1Cable.ver5-change.docx
IBLType1Cable.ver5.pdf
IBL-type1-service_

...

21.xlsx

...

ATUIBLP_0034_IBL_TYPE01_BUNDLE_ASS_v5.pdf
IBL-type1-dimension.xlsx

...

Installation Barber Pole pictures: [1, 2, 3, 4, 5 ]
SLAC-Prod.xlsx

...

Contacts / Practical Info

Building 33 clean room phone ext: x8951