30 min | Status | All | - JF4M assembled....servers available? Parts available for assembly beginning 11/22
- ePix10k Tested at APS. Subsequent tests show solidly operable at 640Hz, not yet giving up on 1kHz.
- Spoke with David regarding wide body RIXS....concerned that scope of integration is not fully understood/accommodated in planning.
- Trying to create compelling case for Tixel for September PEC...taking a long time, ongoing.
- ePix100s forwarded to TID for refurb?
- Need firmware on 10k small to test....status?
- SLAC-level Detector Strategy Task Force: SAC presentation went well, SPC this week, then LDAC.
- DAQ rack plinth set received, fit questionable.
- Seismic table mount components received..to be installed.
- LDAC set for Dec. 3-4.
- Status of 2018 recommendations: 18 closed/complete, 13 in work/on track, 3 deferred/rejected (Doc available).
- NEED:
- RIXS-CCD need analysis of flux limitations (status?)
- 'White paper' on zero-suppression tradeoffs (in work).
- Data analysis on ePix prototypes tested in Run 17.
Status: - RA: Establishing clean area....do not touch items on big table without asking RA first.
- Need to conclude wiring detail. Each wire should be managed.
- Set up a meeting with Dan, Raj to talk over packaging, strain relief.
- Time on drawings....progress ongoing. Four of the big 5 are out....still need 3-d part...looking at making two copies to test machining in house....submit by end of week?
- PH: Writing RIXS Talk. Submitted two in-house proposals...one on TID sensors, one on UXI@MEC
- Also one on thin-crystal heating at CXI.
- Need to discuss acquiring sensors from UXI collaboration.
- Wiring diagram for Jungfrau (Sameen)
- Need automated check on pedestal levels...Jason left and no one has picked up.....PH to follow up with Silke.
- UXI options? Nothing until next year....Liam here this week.
- Silke to establish a couple of data streams to examine performance on dropped shots etc.
- EMP testing confusing, un-grounded CSPAD testing this week...test didn't happen.
- Mike Brown has set up ePix10k and ePix100 on XCS for software development...not done?
- DAQ can run ePix100, ePix10k, Jungfrau....can't yet save data.
- Need to check with Chris about data reduction from Run 17.
- KN:
- ePix interlock tests done successfully.
- Need 7 mode PDUs....lupe to make.
- Getting ready for ePixBig test in-hutch on Wednesday to verify hutch is ready to go in Run 18.
- Need to get Mike and Dan talking to the JF kit...IoC on top of PSI scripts.
- Chicane for Marietta almost ready to install eGun.
- Need to coordinate 4-fiber Wave8 with CDS...single vs multimode.
- Matt Church helping with Wave8 ?? Need to mount close as possible to flange.
- All JF Cables are in work
- ePix10k requires new MPODS, working issue...check again mid November.
- KZ:
- RIXS-CCD Procedure draft complete. Review at next detector meeting??
- RIXS-CCD setup work
- Toolbox organization/reorder scheme.
|