FY13 Budget endgame (Marco)
With the FY13 closing, it's a good opportunity to review the cost incurred and discuss if the spending projection for FY14 are still goodvalid.

Software Schedule
The Software schedule needs to be integrated in the HPS Master Schedule and the tasks require to be linked to the sub-detectors developments. We need to define meaningful milestone that are key to track the progress of the project during its execution. (Maurik, Marco). Maurik's talk at the HPS Meeting 9/25/13

...