- ePixM:
- Beamtime prep, Status:
- Install the ePixM at MFX beam dump
- Scheduled Time: Thursday, September 26, 12 pm - 2 pm.
- Setup check list: Fiber converter (with FTP fiber and 3 tranceivers), Power supply, Keithley Source meter (TID IC lab), power cable
- Before the deployment, check the fit of the masks with the detector unit shell.
- Check the MFX hutch Humidity/Temp sensor to calulate the Dew point. Td = T - ((100 - RH)/5.) T in Celsius.
- Move the setup to the beamtime table
- Next Monday 11am
- Physical setup to secure the camera; (Chris Koerber)
- Test the script for the beamtime data collection;
- Git branch update?
- Setting up the pre-setup meeting (include TID people);
- LCLS Daq for beamtime
- New register setting optimized for dynamic range
- Get the measurement plan (Zongde)
- Drafted https://confluence.slac.stanford.edu/x/MQwtHw
- Measurement Flow Chart (low temperature/humidity/dew point to prevent condensation)
- Schedule the staffing;
- Two-person hutch searching required
- Shift1: Conny, Alex, Kaz, Xavier
- Shift2: Dionisio, Zongde
- Install the ePixM at MFX beam dump
- Beamtime prep, Status: