TopicsNotes
Worry List

Action Items:

  •  All SMs and Owner of the item from the worry list will need to review, update and follow up as needed.
DR Preparation

DR Template

  • What are the 5-6 high level steps that are needed to get you to CD-2/3?  P6 tasks too detailed
  • Cost and Schedule Dashboard - Traci will provide
    • Annotate and use red banner to give high level message
  • Cost comparison - Traci will provide
    • Explain changes.  "TBD" area will be corrected by Traci.
  • One-pager
    • If System is on critical path, presenter should address
  • CD-3A Long Lead Procurements have been identified (HE-LP).  Remainder of procurements are after CD-2/3.
  • Risk table - Karl Flick will provide.  Additional Monte Carlo slides will be provided by Charles.
  • New Challenges Resulting from Notional Funding Profile
    • Include Deliverability Issues as a direct result of flat funding profile
    • Include mitigation issues to address each issue
  • Items Yet to be Addressed
    • No new scope
  • Recommendations from Prior Reviews
    • Laser folks to meet offline to discuss how to present
    • Show the examples most pertinent to charge questions
  • Action Items:
Next TI meeting