Camera | type | Aim | Date at ASC | Previous delivery date | Comments |
|
|
|
| ||
|
|
|
| ||
|
|
|
| ||
ePixHR5kHz Quad | boards only | Integration into DAQ and software testing to allow for expansion to full camera (board integration for DAQ). | August 2023 | May 2023; end March 2023.; Feb 2023;December 2022 | This delivery time is for boards only. |
ePixHR5kHz small prototype | ASIC V4. | Small prototype camera for first testing of ASIC v4. | August 2023 (camera with sensors) | July 2023 (just ASIC, check with kenney about sensor version), June 2023 (pending ASIC submission) | |
ePixHR5kHz full Camera | ASIC v4. | Initial testing of full camera and in lab calibrations. | End of November 2023 |
ePixM camera (5 kHz)
A non thin entrance window detector will be delivered initially for DAQ integration purposes, followed by the cameras themselves, with thin entrance windows. Commissioning is set to start in April 2023. 3 Cameras will be delivered.
...
Camera | type | Aim | Date at ASC | Previous delivery date | Need date in hutch |
ePix10k small, 1mm Si | sidefacer | Added to operations; Commissioned by Sebastien. | Uncleardelivered. | July 2022 | N/A |
ePix10k2M.2 | non-ghosting ASICs | Added to operation; currently aimed at MFX but needs to be discussed with beamlines ones it is delivered. | May 2023 | April 2023; Nov. 2022 | ASAP |
ePixM5kHz | 90 | To be installed at REXS chamber at qRIXS | April 2023 | ||
ePixM5kHz | 0 | To be installed at ChemRixs chamber | April 2023 | ||
ePixM5kHz | ? | To be installed at the end of new (currently not excisting) spectrometer arm next to qRIXS spectrometer arm | At least a year after first ePixM detector | ||
ePixHR5kHz 2M | Large ePixHR5kHz camera | To be installed at TXI. | After start 2024 (chamber delivered start 2024) | ||
ePixHR5kHz small | Small ePixHR5kHz camera; same form factor as side facing ePix100 | To be installed at TXI. | end of 2023. | ||
ePixHR5kHz small | Small ePixHR5kHz camera; same form factor as side facing ePix100 | To be installed at TXI. | end of 2023. | ||
RIXSccd | CCD | System 1, at STA for shimming down the sides and the bolts. | Mid August | July 2023 | October 2023 |
RIXSccd | CCD | System 2, at STA for shimming down the sides and the bolts. | Sept. 2023 (3 weeks after system 1) | August 2023 | TBD |
...
Testing capability schedule
Capability | Type | Aim | Date available | Previous availability date | |
Running LCLS-II detectors at XPP. | LCLS beam line testing | Run fiber from RIXS to XPP so LCLS-II detectors (ePixM, ePixHR) can be tested there | Available | N/A | |
Running LCLS-II detectors at MFX. | LCLS beam line testing | Run fiber from RIXS to MFX so LCLS-II detectors (ePixM, ePixHR) can be tested there | August | Feb-March 2023 | N/A |
Running LCLS-II detectors at FEH. | LCLS beam line testing | Run fiber (DRP solution) from RIXS to FEH so LCLS-II detectors (ePixM, ePixHR) can be tested at MFX/XCS/CXI | June 2023 (subject to availability of installed fiber cable) | N/A | |
E-gun X-ray source | ASC X-ray source | pulsed X-ray source at ASC | TBD |
Beamtime schedule
Experiment number | Station | Aim | Dates | Lead from Ops team side |
X-10025 | MEC | Energy and burst rate frontier using a GaAs Icarus Detector. | 2023: 28 April (Night), 29 April (Day), April 30 (Night), May 1 (Day) | Philip Hart |
| ||||
| ||||
ePixHR | MFX | Evaluate the performance of the ePixHR detector. | 2023: 29 Aug (night), 14+15 Sept. (night); 23Oct. | Conny Hansson |
ePixM | MFX | Evaluate the performance of the ePixM detector. | Early 2024 | Conny Hansson |
ePixM | MFX | Evaluate the performance of the ePixM detector. | March-April 2024 | Conny Hansson |
ePixM | chemRIXS | Evaluate the performance of the ePixM detector. | Before June 2024 | Conny Hansson |
...