| Technical updates |
| - ELI Beamline photos from Eric, Dimitri and Meriame
- Discussion of stalled MEC-U UAP meeting
- Scope conversations
- Kai is asking engineers to refer to a facility not supporting the upgrades in CDR 11.2 not as "FES Base" but rather "FES minus explicitly designed upgrades" ("FES -EDU")
- Cavern space looks very constrained when considering beam delivery, dumping and access.
- Mikael has a request to consider what the impact would be of living in FES -EDU world.
- Requirements transcription into Jama - needing help
- Engineers are working from one incomplete slide deck to figure out requirements - slide deck had a configuration (inadvertently?) deleted back in September.
- As a consequence, Brice was surprised to learn that we might want a dual target for some experiments (e.g. ion heating target)
- Flagship descriptions into Jama. One presentation is here
- Considering a different mirror to put MEC below floor at final FEH location. Discussed this morning
- Very preliminary discussion
|