For the ePixHR camera a prototype small detector will be delivered, followed by a Quad, and finally the full camera. This is done in order to allow for the DAQ integration for the Quad (which is repeated 4 times for the full camera) to begin prior to delivery of the full camera and allow more time for this work. Commissioning is currently set for sometime in the end of 2023 (date to be confirmed), and one large camera and 2 small cameras will be delivered.

Camera

type

Aim

Date at ASC

Previous delivery dateComments

ePixHR5kHz

ASIC v2.

Integration into the LCLS-II DAQ and initial testing to feed into ASIC v3. submission.

April 2022



ePixHR5kHz

ASIC v2.

Integration into the LCLS-II DAQ (new firmware structure) and initial testing.

October 2022



ePixHR5kHz

ASIC v3.

Integration into DAQ and initial testing of ASIC.

November 2022


No longer apply due to v4 ASIC need.

ePixHR5kHz Quad

ASIC v3.

boards only

Integration into DAQ and software testing to allow for expansion to full camera (board integration for DAQ).

end March 2023.

Feb 2023
;December 2022This delivery time is for boards only.
ePixHR5kHz small prototypeASIC V4.Small prototype camera for first testing of ASIC v4.June 2023

ePixHR5kHz

full Camera

ASIC v4.

Initial testing of full camera and in lab calibrations.

May

End of November 2023




ePixM camera (5 kHz)

A non thin entrance window detector will be delivered initially for DAQ integration purposes, followed by the cameras themselves, with thin entrance windows. Commissioning is set to start in April 2023. 3 Cameras will be delivered.

Camera

type

Aim

Date at ASC

Previous delivery date

ePixM5kHz

Not back thinned

Integration into DAQ; Initial ASC performance testing.

Mid May

end March 2023; Feb 2023

ePixM5kHz

Back thinned

Initial testing of the ePixM camera at ASC and in lab calibrations.

September 2023

March 2023

...