QC Test Box XY Stages
01:02 AM May 22, 2021: UNDER DEVELOPMENT BY SANHA (This section serves as a documentation as well as an e-log, while the system is still under development.)
This section documents the set-up and the operation of the XY stages (one for the ring and the other for the stave) in the QC test box.
Contacts: Contact: Sanha Cheong (sanha@slac.stanford.edu), Zhi Zheng (zzheng@slac.stanford.edu)
Set-up Overview
The stages are powered OpenBuilds 24V DC power supplies inside the QC test box. They are also connected via USB to the iMac (running Ubuntu) next to the QC text box and can be controlled by `OpenBuilds CONTROL` software.
Operation & Calibration Procedures
Ring Stage
USB0, Left PS
X: + is down, - is up. steps / mm = 197.04
Y: + is in, - is out. steps / mm = 57.14
Interlocks: X = [-5.21mm, 263mm] Y = [-5.18mm, 410mm]