30 min | Status | All | ePix Update: - Kickoff meeting for ePix fab April 9, 3pm, Kite
- Peter Denes visited last week to discuss SXR imager requirements:
- Notes from last SXR requirements discussion now posted here. Latest version in circulation for review, need to finalize a the end of this week (April 12)
- TES re-baseline document has been reviewed by NIST/CU and some comments have been incorporated. Next step is to forward to LCLS management for approval.
- Costed proposal from Anton for MCP/TImepix tests has been formulated as a PEC briefing...turns out that it doesn't need PEC, so will re-cast as a 'project charter' this week and turn on the funding. Would like to arrange a kickoff meeting, perhaps a road trip to UCB/SSL?
- Update > Status RIXS-CCD test planning
- Masks here, holder ready
- tests last week reached 300Hz operation, not sure of effect on performance.
Status:
- MEC EMP testing CSPAD/ePix Date TBD
- KN Wave8 upgrade for FIM CDR Mid-April
- ePix10k requires new MPODS, working issue
- Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
- eGun interlock doc (2wk.)
Lost cabinets were not delivered....(2wks) Now set for refund and re-order as two rolling tool chestsKZ: Control room furniture install this afternoon. Furniture installed, wall cabinets remain to go.- Status documentation/procedures effort
- How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
|