Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

H4/SPS Daily meetings

 

September

...

7

Status: First day of beam. We were supposed to have the beam at midnight, we got it at 3PM. The timing was looked at, the calorimeter  signal is now coming earlier with respect to the tracker as compared to PS.  BT 5 configutation with cal/tkr in the middle of the trigger window at SPS is now the baseline.The calibration of the calorimeter (cross pattern) at 100 GeV was started then interrupted to let the experts optimize the beam tuning at the highest energies. Many interruptions due to machine problems. Benoit attended the weekly users' meeting (moved from Thursadt to Wednesday as tomorrow is a holiday in Switzerland): there will be machine development (no beam)  from next Tuesday 8 AM to Wednesday 4 PM. A threat on our running with the "0 mrd" configuration (allowing us to get the highest rate at high energy)  was mentioned during the meeting, as the H2 users (sharing the same target) would like a less detrimental configuration for them. Finally, a way around was found and we wil keep this configuration at least until Monday. 

Program: completion of the 100 GeV calibration runs, ACD calibration with protrons+pions, switch to 200 GeV, scanning of different  (X,Y, theta) configurations 

September 7

Status: The beam is now much more stable. Calorimeter calibration completed, ACD calibration completed, scanning of 200 GeV configurations almost completed. Some runs were repeated after it was found that 4 scintillators used for the beam tuning were still in and be moved out. The pressure in the 2 Cerenkovs (1.2 bars so far) was set to 0. The dependence of the calorimeter measured energy as a function of rate has been investigated ("baseline restoration" problem). The effect is clearly visible. We decide to limit the rate to 400 Hz for the rest of the run. The time of the daily meeting will be moved to 5 PM to enable people on the previous night shift to attend.  

Program: switch to 280 GeV and repeat  the same configurations. Specific BT configuration files will be prepared by Luca and Carmelo to study the FHE efficiency using the SPS timing settings. As proposed by Anders, the TEM diagnostics will be on by default (BT 6 which is now the baseline).

The beam is now much more stable. Calorimeter calibration completed, ACD calibration completed, scanning of 200 GeV configurations almost completed. Some runs were repeated after it was found that 4 scintillators used for the beam tuning were still in and be moved out. The pressure in the 2 Cerenkovs (1.2 bars so far) was set to 0. The dependence of the calorimeter measured energy as a function of rate has been investigated ("baseline restoration" problem). The effect is clearly visible. We decide to limit the rate to 400 Hz for the rest of the run. The time of the daily meeting will be moved to 5 PM to enable people on the previous night shift to attend.  

Program: switch to 280 GeV and repeat  the same configurations. Specific BT configuration files will be prepared by Luca and Carmelo to study the FHE efficiency using the SPS timing settings. As proposed by Anders, the TEM diagnostics will be on by default (BT 6 which is now the baseline).

Analysis: the first quick comparison with the MC simulations at 100 GeV shows a reasonable agreement for the tracker hit multiplicity (the multiplicity is larger for the data) and the energy deposited per layer in the calorimeter.  No comparison is available for the ACD yet.  More simulations are needed.   

September 6

Status: First day of beam. We were supposed to have the beam at midnight, we got it at 3PM. The timing was looked at, the calorimeter  signal is now coming earlier with respect to the tracker as compared to PS.  BT 5 configutation with cal/tkr in the middle of the trigger window at SPS is now the baseline.The calibration of the calorimeter (cross pattern) at 100 GeV was started then interrupted to let the experts optimize the beam tuning at the highest energies. Many interruptions due to machine problems. Benoit attended the weekly users' meeting (moved from Thursadt to Wednesday as tomorrow is a holiday in Switzerland): there will be machine development (no beam)  from next Tuesday 8 AM to Wednesday 4 PM. A threat on our running with the "0 mrd" configuration (allowing us to get the highest rate at high energy)  was mentioned during the meeting, as the H2 users (sharing the same target) would like a less detrimental configuration for them. Finally, a way around was found and we wil keep this configuration at least until Monday. 

Program: completion of the 100 GeV calibration runs, ACD calibration with protrons+pions, switch to 200 GeV, scanning of different  (X,Y, theta) configurations Analysis: the first quick comparison with the MC simulations at 100 GeV shows a reasonable agreement for the tracker hit multiplicity (the multiplicity is larger for the data) and the energy deposited per layer in the calorimeter.  No comparison is available for the ACD yet.  More simulations are needed.  

T9/PS run Daily Briefings - 3PM

...

 Communications

 - Magnet failure: MNP17 colling system failure at 1AM stopped data taking for several hours but no damage on hardware. Physics restarted after 2 hours w/o silicon tagger for CAL calibrations. Magnet repaired in the morning
- CU cooling system changes: CU/ISC cooling coil in the ISC base plate leaked: it was emptied and is now non available, we will rely on top cooling coil as no intervention is possible; the chiller was moved closer to the ISC to minimize thermalization of coolant with ambient through thermal exchange with the zone air, now chiller more efficient;  fan added to cool XY table motors. Please look at the temperature during your shift

 Online Report

 - DAQ sync studies going on
- CU: Ric investigating phasing errors

 Offline Report

 Francesco:
- pipeline  nicely running
- 1st 1000 evetns in SVAC ntuple duplicated  
Claudia: 
- offline monitor requires script to parse rcReport info and link to MC files (Navid working on that)
- MC and CU cooprdinate systems mismatch (check with Philippe) 
Dave:
- no CAL-HI triggers in last night data as  fhe values were saturated

 Program

 - Complete DAQ sync studies
- perform CU timing studies to optimize TACK (timing/script vs ext trigger manual delay)
- explore beam conditions 
- ACD calibrations (ideally 5gev p, if NA 5gev e) 
- CAL runs with e (Benoit)
- Tagger calibration start on 29 morning

Notes 

 - Fill elogbook
- Take your shifts and launch runs yourself 
<ac:structured-macro ac:name="unmigrated-wiki-markup" ac:schema-version="1" ac:macro-id="c243c068d92da4ac-69ca0803-48c447a5-ba3ba0d0-c44f74624d227a9910939ab0"><ac:plain-text-body><![CDATA[- rcReport has wrong table positions for runs [701-736]; the right correlation table between position and run will be circulated. Please reset runcontrol before starting a new run when you change conditions (table position, beam configuration, trigger, CU conf)

]]></ac:plain-text-body></ac:structured-macro>