T9/PS run Daily Briefings - 3PM

 
Daily briefing minutes

August 11 - 32-S-C22

 Communications

- Running since this morning 9AM with 2 spills, 3 spills available since 2.30PM. Currently taking tagged photons from 1GeV e beam.

- 60K evts of 2.5GeV e taken for reference after shutdown
- Sh became inefficient and empty events were triggering the si tagger; S3 is now isntalled as a veto over the S2 light-guide (Nicola M)
- verified feasibility of 500MeV beam: rate is ok but beam is larger, will have to verify if S3 veto is ok and final tagging rate
|

 Online&DAQ Report


 OfflineReport


 Program

- agreed program here

 Notes 


August 10 - 13-3-005

 Communications

  News from PS/PS Users Meeting:
-intervention on QED2 scheduled to end 5PM; spare was found to be not working, a second spare was available but needs to be equipped with a new vacuum chamber that will be taken from the 1st non good spare
- beam loss in the separation magnet between east hall south and north branch; currently this is the reason why we have no beam; if replacement of QED2 cures the loss we should get beam back tonight, otherwise a technical intervention will be required, and cooling time is 4 days minimum (currently the radiation level at the separation magnet is 2mSv)
- supercycle changes: agreed changes for next week so that we get 3 spills in east hall during working hours and 4 during night and week-ends; the fourth spill will come around 4 sec later that the first three. new changes wil be discussed for week 34 (check weekly schedule here)
- Luca to investigate on the possibilty of an extension with the MICE group which is supposed to run after GLAST 

 Online&DAQ Report

Ric confirms that agreed modifications on spill structure for next week will not hamper DAQ sync and data merge online

...

 Communications

 - Magnet failure: MNP17 colling system failure at 1AM stopped data taking for several hours but no damage on hardware. Physics restarted after 2 hours w/o silicon tagger for CAL calibrations. Magnet repaired in the morning
- CU cooling system changes: CU/ISC cooling coil in the ISC base plate leaked: it was emptied and is now non available, we will rely on top cooling coil as no intervention is possible; the chiller was moved closer to the ISC to minimize thermalization of coolant with ambient through thermal exchange with the zone air, now chiller more efficient;  fan added to cool XY table motors. Please look at the temperature during your shift

 Online Report

 - DAQ sync studies going on
- CU: Ric investigating phasing errors

 Offline Report

 Francesco:
- pipeline  nicely running
- 1st 1000 evetns in SVAC ntuple duplicated  
Claudia: 
- offline monitor requires script to parse rcReport info and link to MC files (Navid working on that)
- MC and CU cooprdinate systems mismatch (check with Philippe) 
Dave:
- no CAL-HI triggers in last night data as  fhe values were saturated

 Program

 - Complete DAQ sync studies
- perform CU timing studies to optimize TACK (timing/script vs ext trigger manual delay)
- explore beam conditions 
- ACD calibrations (ideally 5gev p, if NA 5gev e) 
- CAL runs with e (Benoit)
- Tagger calibration start on 29 morning

Notes 

 - Fill elogbook
- Take your shifts and launch runs yourself 
<ac:structured-macro ac:name="unmigrated-wiki-markup" ac:schema-version="1" ac:macro-id="24572471e0f7f63b-5641445a-4eb04eee-a5198cb9-70dfd318cbd7605de8990e3a"><ac:plain-text-body><![CDATA[- rcReport has wrong table positions for runs [701-736]; the right correlation table between position and run will be circulated. Please reset runcontrol before starting a new run when you change conditions (table position, beam configuration, trigger, CU conf)