Communications | No beam since this morning at 9. CUrrent estimation is NO beam before tomorrow afternoon, shifts are suspended, we will restart tomorrow at 12 and update. |
Online&DAQ Report | DAQ sync with AD ran smoothly since this morning at rates up to 1500 part/cycle, corresponsind to a peak rate of 1KHz (max is 2K), with a beam intensity of 60KHz |
OfflineReport | - Latency for full-brem runs is large due to caltuple merge, Luca to investigate with Francesco if pipeline can be coinfigured to link to merit and SVAC tuples before merging caltuple; the other option is to give up the CAL tuple (to be discussed with CAL people) |
...
Program | - agreed program here |
Notes |
...
Communications | Beam back from9. Standard beam with 3 spills from 11. Discovered that magnet settings were wrong and gave beam crossing cerenkov detectors therefore reducing e fraction and trigger efficiency. After loading the magnet settings file from Erik everything was fine and we could restart. |
Online&DAQ Report | DAQ sync with AD ran smoothly since this morning at rates up to 1500 part/cycle, corresponsind to a peak rate of 1KHz (max is 2K), with a beam intensity of 60KHz |
...
Communications | - Magnet failure: MNP17 colling system failure at 1AM stopped data taking for several hours but no damage on hardware. Physics restarted after 2 hours w/o silicon tagger for CAL calibrations. Magnet repaired in the morning | |
Online Report | - DAQ sync studies going on | |
Offline Report | Francesco: | |
Program | - Complete DAQ sync studies | |
Notes | - Fill elogbook | ]]></ac:plain-text-body></ac:structured-macro> |