Date | Room | Communications | Online report | Offline report | Run program | Notes |
---|---|---|---|---|---|---|
july 28 | 13-3-05 005 | - Magnet failure: MNP17 colling system failure at 1AM stopped data taking for several hours but no damage on hardware. Physics restarted after 2 hours w/o silicon tagger for CAL calibrations. Magnet repaired morning | - DAQ sync studies going on | Francesco: |
Wiki Markup |
---|
\- MC and CU cooprdinate systems mismatch (check with Philippe) Dave: \- no CAL-HI triggers in last night data as fhe values were saturated\\ | \- Complete DAQ sync studies |
...
\\ \- perform CU timing studies to |
...
optimize TACK (timing/script vs ext trigger manual delay)
\- explore beam conditions
\- ACD calibrations (ideally 5gev p, if NA 5gev e)
\- CAL runs with e (Benoit)
\- Tagger calibration start on 29 morning | \- Fill elogbook
\- Take your shifts and launch runs yourself
\- rcReport has wrong table positions for runs \[701-736\]; the right correlation table between position and run will be circulated. Please +reset+ runcontrol before starting a new run when you change conditions (table position, beam configuration, trigger, CU conf) |
|
July 26 - room 13-2-005
10:30 : Safety visit from CERN: minor action items being followed by Luca L.
...