T9/PS run Daily Briefings

 

 Date

Room

 Communications

Online report

Offline report

Run program

Notes

 july 28

13-3-05

- Magnet failure: MNP17 colling system failure at 1AM stopped data taking for several hours but no damage on hardware. Physics restarted after 2 hours w/o silicon tagger for CAL calibrations. Magnet repaired morning
- CU cooling system changes: CU/ISC cooling coil in the ISC base plate leaked: it was emptied and is now non available, we will rely on top cooling coil as no intervention is possible; the chiller was moved closer to the ISC to minimize thermalization of coolant with ambient through thermal exchange with the zone air, now chiller more efficient;  fan added to cool XY table motors. Please look at the temperature during your shift

 

 

 - Complete DAQ sync studies
- perform CU timing studies to optimize TACK 

 

 

July 26 - room 13-2-005

10:30 : Safety visit from CERN: minor action items being followed by Luca L.

...