Imre supplied this list after his oral presentation:
- Finalizing the Jens Norskov Scientific Computing installation
- Installing Yunhai Cai's new Scientific Computing environment
- Almost finished with the transfer of all Babar data from the old tape silos to the new 8500's.
- In January the old tape silos will be removed from building 50 freeing nearly 2000 square feet
- Completed adding 900 KVa to the building 50 DC, with another 1 Mw on the way by next summer.
- The SRCF datacenter build project is in design-phase, completion scheduled in 2013.
- Citrix Xen App 6.0 upgrade is scheduled to be completed early January
- Windows 7 and IE8 phased rollout will begin early January (new builds and special requests)
- Departmental Support is involved in Sandy's Centralized Support (CMFD) program, working first with SSRL, AD and Pulse
- The AT&T permanent cell antenna and a new Verizon permanent cell antenna are being installed on building 50.
- Hector Prado has been selected as IT Departmental Support manager and Antonio Cesaracciu as our new Network Architect
- IDOL Search has been implemented for our web sites, later may be rolled out to cover SharePoint and confluence
- Instant Messenger federation by implementing OCS 2007 early next year
- Database roadmap completed and placed to EAhome
- WCM Roadmap is close to completion
- Crowd for confluence will be implemented early next year
- Lsoft Listserv replacing Majordomo early next year
- Scientific Funding Model is being simplified and comments added for use by the office of the CFO
- ITIL processes are being looked at, we are constructing a roadmap to determine its value, sequence of implementation and cost
- Technical Design Review process has been developed and will be implemented starting in January
- Technology Roadmapping (longer term planning ) methodology has been implemented
- Strategic Sourcing project is in vendor selection phase. Goal make decision about and plan the future of the SLAC ERP system
- Electronic timecards project selected SaaS vendor (vorksoft)
- New head of IT project office has been hired (Kathy Nakazawa)
- Selection of Secure Web Gateway (CPP sensor) is ongoing
- BaBar LTDA project ongoing
- Forum tool selection is ongoing
- Google analytics has been implemented on most of our web sites
- SLAC lectures are available on streaming video
- Taleo's recruitment module planned to be implemented early next year
- IT created the first draft of its Service Portfolio for review by the IT Sub-council
- Travel system improvements under way
- Direct deposit system is being implemented (travel expense reimbursement via direct deposit)
- Number of pagers across the lab has been reduced from ca. 500 to ca. 200
- Les looked at other labs IP management strategies/tools and will provide summary
- Data Loss Protection solution has been partially implemented
- Xpression training is coming