Date
Attendees
Discussion items
- Reminder: dosimeter swap time!
- Discussion about our first week of running
- 2K compressor tripped at the end of day shift yesterday: heat related
- Tripped high on processor frequency for VFD
- Cooled on building air
- Pumped down yesterday, went well
- Magnets restarted this morning
- Will re-start SRF tomorrow - have a couple of hours tomorrow morning blocked out
- AMRF will be ready to join us at 8:15
- ACM work during day shift, injector work this afternoon
- AMRF had a meeting to dole out remaining tasks after the SRF restart
- HLs might have more issues to be CATERed - turn on was interrupted by cryoplant trip
- Nonlinearity on SSAs on CMH1-4 and another one
- Another SSA came back with low power
- Any work on CM01 LLRF? No.
- Maybe laser locker work impacted LO levels
- A few of us noted that SSA drive maxes were sort of low (unnecessarily) - maybe we should go through and check these again?
- Multipact processing
- Maybe we can start in the morning?
- Names for each shift in calendar
- Can't do RF inspections for HE CMs tomorrow due to other work scheduled in 750
- Meet Weds during the PAMM
Action items