Time | Item | Who | Notes |
---|
5 min | Misc | Sebastian | - Get yubi key
- Check 219 training
- Performance evaluations
- two weeks to get personal evaluations done
- Haley starts next Monday
|
20 | Processing | Sebastian and Ryan | - Multipacting processing sometime around restart
- Before or after beginning of Oct
- Oct 5 is the SC restart
- Two weeks before this, or part of linac restart
- Shielding for vertical transfer line may not be done?
- We quench and reset during processing to clean the surface
- Do not want to field emit though, so need to watch this process carefully
- Ryan looked at which cavities have potential for most gain
- ~104 cavities, 71 have already demonstrated going to ~18 MV/m
- This is promising for reaching higher gradient.
|
2 | Misc | All | - Plan intern tunnel tour (Jonathon, Felicity, Carina, Soham)
- SLACPAS next week
|