Attendees:

Mikael David Martinez Conder, Alan Dean Alex Wallace Hardin, Corey L. Hill, Elizabeth Jing Yin LaFortune, Kai Nicholas Greenberg, Michael R. Mitchell Cabral Selina Green Yang, Steven Shofman, Vadim Ginger DeContreras 

Technical Path to DR and OPA Reviews

TopicsNotes
Worry ListSystem Managers to ensure that all concerns with new funding profile are captured.
Alternate PlansTI team will discuss additional plans.

Documentation:

WBS Dictionary - need at Control Account level.  Exclude deferred scope.  Include approved BCR items.

  • Experimental Systems:  Corey to check, close by this week.
  • Laser:  Steven to follow up with Brice (Laser Transport).  Liz done (HE-LP).  Justin in progress and closing this week (RRL).
  • SLAC Controls:  Jing reports complete.  Need to follow up with Barry (RRL Controls).  Nate up to date (RRL Controls).

Documents (PRDs, ICDs, ESDs, etc.) - need updates.

Review Recommendations

Will be developing plan to answer/update these recommendations

Change Control

Workshop scope will be officially in the plan and will go through BCR/CCB process.

No additional BCRs until after reviews.

Continue running TCCBs as needed, add to Pending Log.