Install

  • Verify power off.  (MPOD panel or IoC panel)
  • Install detector in experimental setup, consulting with beamline scientist.
  • Connect gas line if applicable, start flow at 5l/m.
  • Connect chiller, start flow.  Set temp to 15C.
  • Connect data fiber.

Power

  • Set known values on mpod.
  • Pin out cable according to diagram.
  • Turn off mpod.
  • Connect power cable to detector.
  • Set operating voltages on mpod.
  • Start DAQ and configure to begin idle.

Stabilize for 15 minutes

Record Voltage/Current/Temperature Values

Measure and Apply Pedestals

Update Traveller