30 min | Priorities Review | All | - 2021-2 events:
- Projects new starts:
- ePixM project plan submitted, baselined in P6. Mech design review held Jan 24 (actions circulated). Received sensor wafers from L-Foundry, dicing.
- SparkPix-S Phase II (full-size ASIC for sparsification engine), on-track
- ePixHR V: beamline test completed, data analysis slow.
- TXI Detectors (2Mp and 140kp based on ePixHR @5kHz) Wafer purchase order placed, delay to delivery of about 3 months, other things likely to slip as well.
- ePixUHR (130nm TSV structure to reach 100kHz), CDR completed, PEC approved start, project underway.
- ePix100 integration into LCLS-II DAQ, software and firmware work underway. cpo has etch9.
- Production:
- spare ePix10k modules (0.5 & 1mm) Module order in work, new sensor order delayed. First batch of no-ghost received, now packaging and wirebonding.
- Approved 3d copy of ePix10k2m: underway, March delivery (slipped due to module delay, PCB issues)
- Approved spare quads for MEC: delivered, in test.
- Proposed in-air 2m/1mm project plan submitted to OIP.
- Proposed UED detector upgrade, planning in work.
- Proposed ePix10k4m (concept)
- RIXS-CCD/cooler test and verification: Second unit in test. Vibe seems moderately worse, but OK. Working on test report, and review with NEH2.2.
- HiZ collaboration tests: Ge and CZT beamtime completed, analysis in work (plan?). Lab tests ongoing.
- Outreach for R&D support (SparkPix-ED, SparkPix Delta).
- SBIR effort for UXI not funded.
- Group priorities review:
- Testing
- Develop workable version of 'standard' cal script, test on 10k small, Bhavna: Possible to demonstrate by week of Feb 14?
- Preparation for IH UXI, Philip, possible to get contract set and engineering work set by week of Feb 14?
- Air-scatter CompEnOn study to refine timing...Philip/Bhavna, possible to complete analysis by week of 2/14?.
- Acceptance test new quads Bhavna, possible to complete basic cal (pedestals, charge-injection) floe by week of 2/14?
- Test second RIXS-CCD: Kaz/Chris: possible to take/analyse 2d data set incl vibe by week of 2/14?
- Analysis
- Gather new data to support calibration constant development (air-0scatter, FoLo, ??)
- Documentation
- Complete on-line travellers for Mp detectors
- Development
- Hi-Z test data analysis (Conny, is there a reasonable target for week of 2/14?
- Testing ePixHR in our lab: Conny, is it possible/worthwhile/important enough to try to get it running in our lab by week of 2/14??
- Lab 'commissioning'
- DAQ
- Get water and power completed in mech chase (reasonable milestone by 2/14?)
- Marietta interlocks for Kimball. Need to check with Jenna
- Marietta fixturing for calibration of epix, JF smalls
- Vac chamber for in-lab tests? Compatible with XPP alcove? Chris/az/Philip/Cony confer and select config by 2/14??
Actions:
|
30 min | Status |
| No update on dept head recruiting. Taking vacation time on Fridays. Save some time at the end for OIP list input? Lab focus on organization/clutter - lab cleanup day on thursday. Complete tests on RIXS-CCD this week and store safely - carry archon and cable over to 2.2 to check fit Chiller issues in UED not reproducible in lab.....compare pressure readings? Opportunity to focus on lagging priorities: Marietta/Kimball, water/power, RIXS-CCD data analysis/reporting, beamtime data analysis, vac test chamber? Status on water/power?? Topics for Cal team meeting? Bojan to join going forward.
KN: - No timing in ASC...probably due to power issues in NEH.
- Rayonix shipped.
- Hunting for ePix small vac hardware....some parts missing.
PH: - Getting ready for UXI test...no GaAs available unfortunately
#CH: - Christmas tree setup for Ge
- Flex cable may be too short....will check today.
- HR camera back to TID.
- Boards being modified for HV CZT
- NYC 10/14-20.
#RA: - Need mtg for acceptance test planning (Friday)
BN: - Looking at FoLo data, still tryng to parse/understand
- Went through fluorescence process.
- Min/max stitching.
- Run cal on new ePix firmware.
- Grafana setup to alert Slack channel.
- Made updates to detector website, in work.
- Working with PH on porting PyRoot to Python.
CK: - Setting up vac components for RIXS-CCD.
- Trying to get cables complete for CSPD/CXI
- Trying to move water/power effort in chase.
|