Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
10 minBeamtime support update

30 minPriorities ReviewAll
  • 2021-2 events:
    • Projects new starts:
      • ePixM project plan submitted, baselined in P6.  Mech design review slips to Jan 20 (panel availability). 
      • SparkPix-S Phase II (full-size ASIC for sparsification engine), on-track
      • ePixHR V:  beamline test completed.
      • TXI Detectors (2Mp and 140kp based on ePixHR @5kHz) Wafer purchase order placed, delay to delivery of about 3 months, other things likely to slip as well.
      • ePixUHR (130nm TSV structure to reach 100kHz), CDR completed, PEC approved start, project underway.
      • ePix100 integration into LCLS-II DAQ, software and firmware work underway.  cpo has etch9.
    • Production:
      • spare ePix10k modules (0.5 & 1mm) Module order in work, new sensor order delayed.  First batch of no-ghost received, now packaging and wirebonding.
      • Approved 3d copy of ePix10k2m: underway, November delivery (may slip due to module delay)
      • Approved spare quads for MEC: delivered, in test.
      • Proposed in-air 2m/1mm project plan submitted to OIP.
      • Proposed UED detector upgrade, planning in work.
      • Proposed ePix10k4m (concept)
    • RIXS-CCD/cooler test and verification:  Second unit in test.  Working on test report, and review with NEH2.2.
    • HiZ collaboration tests: Ge and CZT beamtime completed, analysis in work (plan?).  Lab tests ongoing.
    • Outreach for R&D support (SparkPix-ED, SparkPix Delta).
    • SBIR effort for UXI not funded.


  • Group priorities review:
    • Testing
      • Develop workable version of 'standard' cal script, test on 10k small, log in tracker.
      • Air-scatter CompEnOn study to refine timing.
      • Acceptance test new quads
      • Test second RIXS-CCD
    • Analysis
      • Gather new data to support calibration constant development (air-0scatter, FoLo, ??)
    • Documentation
      • Complete on-line travellers for Mp detectors

    • Development
      • Hi-Z test prep
    • Lab 'commissioning'
      • DAQ
        • Get water and power completed in mech chase
      • Marietta interlocks for Kimball.
      • Marietta fixturing for calibration of epix, JF smalls
      • Vac chamber for in-lab tests?  Compatible with XPP alcove?


Actions:


30 minStatus

Covid bloom scarceness...any issues or questions?  ~70 cases since winter closure began (compared with ~40 previous).  Campus >1k cases.  Pls use health check to let lab know if you test positive outside of color tests.

Opportunity to focus on lagging priorities:  Marietta/Kimball, water/power, RIXS-CCD data analysis/reporting, beamtime data analysis, vac test chamber?

mgmt mtg included triennial review highlights....including minor shout out to detector department

LDAC report received.  Generally positive, cautions about Hi-Z options, other items.  working though it now.

Goals entered, thanks.  Schedule talks soon.

Status on water/power??  Omar asked.

Topics for Cal team meeting?  Lorenzo or Bojan to join going forward.



KN:

  • No timing in ASC...probably due to power issues in NEH.
  • Rayonix shipped.
  • Hunting for ePix small vac hardware....some parts missing.

PH:

  • HR beamtime lessons learned on Friday
  • HR test overall quite successful
  • Working on input for LDAC talks
  • UXI IH put in for Run20....could let us offer UXI for user experiments??

#CH:

  • Christmas tree setup for Ge
  • Flex cable may be too short....will check today.
  • HR camera back to TID.
  • Boards being modified for HV CZT
  • NYC 10/14-20.

#RA:

  • Need mtg for acceptance test planning (Friday)

BN:

  • Looking at FoLo data, still tryng to parse/understand
  • Went through fluorescence process.
  • Min/max stitching.
  • Run cal on new ePix firmware.
  • Grafana setup to alert Slack channel.
  • Made updates to detector website, in work.
  • Working with PH on porting PyRoot to Python.

CK:

  • Setting up vac components for RIXS-CCD.
  • Trying to get cables complete for CSPD/CXI
  • Trying to move water/power effort in chase.


5 minBudget Updatemmck
  • M&S Status (Through July)



  • Labor snapshot (July actuals):


15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business

Action items: