Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
20 minDeployment 3-wk planTeam

Shift coverage this week.

  • F 0730: LV95 (Schriber), @CXI JF4M, on-call
  • F 0730: X421 (Diling) @XPP ??
  • F 2100: LV60: (Reinhard) @XCS ??
10 minOther beamtime-related 
  • Wave8 testing/status?
  • ePix10k
    • DAQ/IOC saga update?
    • 2m.1 in repair
    • Constants status/plan?
    • Charge-punch status?
  • Baseline JF and 2M 'traveller' pages on Confluence.
    • Collect and analyze any remaining in-lab test data.
      • Next detector deployed: Kayla to lead meeting for mapping detectors to experiments
30 minPrioritiesAll
  • Group priorities review:
    • Testing
      • Setup ePix10k, ePix100, JF smalls for test in lab (~there)
      • UED testing provision (meet 1430 today)
      • Baseline tests on smalls pre-deployment.
      • Parametric performance tests (10k first)
    • Analysis
      • Gather and process relevant commissioning data for Mp travellers on Confluence.
          • Solid pedestals
          • Noise map
          • Response uniformity (mini-X cu-fluorescencce)
          • Bootstrap gain (sealed source)
          • Linearity (signal injection)
    • Documentation
      • Complete on-line travellers for Mp detectors

    • Development
      • RIXS-CCD, review draft Project Plan w/NEH 2.2
      • RIXS-CCD Concept Design (R to set meeting to talk cooling options)
      • Anton project at UCB/SSL (milestone/schedule revision received)
      • SXR Downselect prep

    • Lab 'commissioning'
      • DAQ
        • Storage nodes
        • LCLS I/II compatibility
      • Table seismic
      • Laser table re-cert
      • BIO for racks in chase
      • DP node purchase
      • Sealed source purchase (M&S evaporating)


Actions:


30 minStatus 

CH: (Are we ready tot fix dashed line issue in the hutches?)

  • Charge injection scripts on 10k smalls for mask tests.

 

RA: (Are we on trac for Lin tests, and when to schedule him?)

  • Loan stages to CXI....ensure return.
  • Meet re cooling concepts...met with Jim re outside space: not much.

 

KP: JSA summary list circulated

  • XPP/MFX/XCS fibers due this week, other wise need ugly solution.
  • Small Rayonix testing can be done by others.
  • XPP/XCS power cable pinout (controls needs to tell us MPOD working)

 

KN:

  • UED Quad now running on our DAQ (LCLS-II)...no 2m when quad testing going on due to PDU channel limit.
  • Replace PDU and cable in XPP to address 10A draw on Pix100
  • XCS IOC: Immediately trips when IOC is running, suspect software problem but not fully isolated.

PH:

  • Learning NERSC interface
5 minBudget Updatemmck
  • M&S Status (Through July)



  • Labor snapshot (June actuals):


15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business  

Action items