Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minStatusAll
  • Jungfrau and ePix2M sensors installed....ePix delivery expected this week. Need to plan testing of JF and ePix w/limited DAQ resource.
  • (Still) trying to hammer out a collaborative proposal for Hi-Z detector development with BNL...slow process.
  • Priorities:
  • Jungfrau, Jungfrau, Jungfrau. (review punch list?)
  • Calibrations/procedure developments for detector deployments, starting with ePix. Kayla out this week.
  • Wave8 readiness.
  • Water leaks in chase??
  • RIXS-CCD ICD/requirement definition. Preliminary meeting held last week, more to come.
  • DAQ rack set-up in chase.
  • Seismic table mount components received.

  • Status:
  • RA: Silke help with scheduling interns...
    • Need help with test plan and verification of J-Box plans for install.
  • PH: Collaboration meeting in ABQ....
    • Writing RIXS Talk. Submitted two in-house proposals...one on TID sensors, one on UXI@MEC
    • Calibration discussions w/ KP.
    • Cable drawing standards have been changed....need updates?

  • KN:
    • Need to get Mike and Dan talking to the JF kit...IoC on top of PSI script
    • eGun installed in Marietta....need to buy HiCube 80.
    • All JF4M Cables are in. Making second umbilical?
    • MPOD cables ....need Hi-V cables for ASC and MFX....follow up with Lupe.

  • KP:
    • Working procedures/calibration with Philip.
    • Working docs with Silke for online access.
5 minBudget Updatemmck
  • M&S Status (Through December)



  • Labor snapshot (Dec. actuals):


15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business  

Action items