30 min | Status | All | - User start date now 5/7. Need to keep foot on the gas.
- Hansson H1-B approved, looks like mid-March start date.
- Widebody RIXS order got in under the wire at DALSA. Need to focus on ICD/requirements definition.
- JF4M assembly in work. Issues? Parts received? DAQ status?
- ePix10k production work on track, Delivery Feb 1 +/- 1 week.
- Trying to hammer out a collaborative proposal for Hi-Z detector development with BNL...slow process.
- Priorities:
- Jungfrau, Jungfrau, Jungfrau. (review punch list?)
- Calibrations/procedure developments for detector deployments, starting with ePix.
- Wave8 readiness.
- Water leaks in chase??
- RIXS-CCD ICD/requirement definition.
- DAQ rack set-up in chase.
- Seismic table mount components received.
- Status:
- RA: Silke help with scheduling interns...
- Need help with test plan and verification of J-Box plans for install.
- PH: Collaboration meeting in ABQ....
- Writing RIXS Talk. Submitted two in-house proposals...one on TID sensors, one on UXI@MEC
- Calibration discussions w/ KP.
- Cable drawing standards have been changed....need updates?
- KN:
- Need to get Mike and Dan talking to the JF kit...IoC on top of PSI script
- eGun installed in Marietta....need to buy HiCube 80.
- All JF4M Cables are in. Making second umbilical?
- MPOD cables ....need Hi-V cables for ASC and MFX....follow up with Lupe.
- KP:
- Working procedures/calibration with Philip.
- Working docs with Silke for online access.
|