Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minStatusAll

Single 90 min meeting going forward, rather than two 60min meetings?

ePix Update:

    • Sensor wafers for 10k big have finally shipped. This is critical path, so parallel flip-chip run has been added.
    • New mechanical engineer added for bigs/quads. Look to schedule meeting to pass on info/concerns.
    • Still to consider:
      • $3k for metrology of existing ePixBig (FY19)
      • $25k to formally release ePixBig drawings/models in TeamCenter (FY20)

    • Testing has begun on ePixHR: ASIC runs at 4kHz. Suspect another iteration will be necessary to get to 5kHz. This is perhaps the fastest x-ray backend to date? Tests continue.
    • Need to re-baseline the ePixHR Phase IV
  • SXR requirements doc signed off by Peter, in review by Angelo..
  • TES re-baseline document not yet forwarded to LCLS mgmt. I'm late on this.
  • Project document for MCP/TImepix is in review with UCB finance. Need to get funding rolling, slow response from UCB.
  • Costed proposal from VFCCD received....lots of spending in FY 19 that will be hard to accomplish. Project charter agreed, morphing to PEC.
  • 10k smalls found...can we run them??
  • Need to conclude the fiber saga.....collect items from Ernesto and TID (timing crate)? (do fibers run from detector lab to laser lab??)
  • Status of 'buy' list?

 

 

Status:

  • RA: Looking at internal temp of airbox and sensor coldplate....agreed that 30C for the hottest pixel is the temp requirement.
  • Need to use 700W chiller for JF4M
  • BIO done. Ready to anchor legs. Tech not available
  • Change request to 15mm central hole
  • CXI stage can't handle CSPAD weight, crane overloaded, no obvious plan.

    JF is focus for foreseeable.
    Wavefront sensor work with Matt Seaburg.

    JF interface document development....where do we want to draw the line? MEC EMP testing CSPAD/ePix Date TBD


  • PH: SDD detector running in lab....ready for egun testing
  • EMP testing confusing, but 10k didn't fall over. SIlke and Mike Brown helping.....
    CSPAD Quad given to TID for isolation/testing as next stage.
    Omar says no CDS netwrok with fibers...true?
  • RIXS-CCD report can be done by 6/30
    Mike Brown has set up ePix10k and ePix100 on XCS for software development...not done?


  • KN: Wave8 for FIM ?? Review conducted....small action list, seems on track.
  • Laser setup done except training.
  • KZ: Draft RIXS CCD procedure completed.
    ePix10k requires new MPODS, working issue
  • Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
  • eGun interlock doc (2wk.)
  • Status documentation/procedures effort
  • How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)

  • KZ: RIXS-CCD Procedure draft complete. Review at next detector meeting??
  • RIXS-CCD setup work
  • Toolbox organization/reorder scheme.
  • Consumables supplies received.
  • Can't get dessicator or table legs anchored due to tech availability.
  • Move guest chamber and stand into lab with riggers help

gone 6/5 - 6/9, 6/15-21

5 minBudget Updatemmck
  • ASC: $268k cost + committs, $14k is in error and will be removed. Asking PA account be closed.
  • Detector I&D (16159): $221k costs + commits ($401k budget)
      • M&S $84k costs + commits ($142k budget)
      • Labor:$111k ($80k budget)
      • Shop:$35k ($66k budget)
  • Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business  

Action items

  • Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster