Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minStatusAll

 

ePix Update:

    • Met with Chris Kenney last week: Sensors for bigs are late. These were ordered last July and expected delivery was in January. Other tasks are late getting started, partially due to late start of funding, but not critical path.
    • Testing to begin on ePixHR soon: Boards being loaded with test chips last week, testing may start this week.


  • SXR requirements doc now has outgassing and envelope info supplied by NEH 2.2

  • TES re-baseline document has been reviewed by NIST/CU and some comments have been incorporated. Next step is to forward to LCLS management for approval.
  • Costed proposal from Anton for MCP/TImepix tests has been formulated as a 'Project Charter' per Su_Ping's templates...in review by Su-Ping prior to releasing funding. Need to set up a visit to kick this off.

  • Update > Status RIXS-CCD test planning
    • Primary tests last week identified grounding problem. Optimization?
    • No strong dependence of noise on temp or frame rate uncovered yet.
    • Need to brainstorm and acceptance test plan this week.

Status:


  • RA JF interface document development....where do we want to draw the line?MEC EMP testing CSPAD/ePix Date TBD
  • KN Wave8 upgrade for FIM CDR Mid-April
  • ePix10k requires new MPODS, working issue
  • Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
  • eGun interlock doc (2wk.)
  • Status documentation/procedures effort
  • How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 minBudget Updatemmck
  • ASC: $260k spent, $2k remains (costs plus commits....some of the commits have already been received (chairs)....will check with Sallie if these haven't posted by next month.
  • Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 minReview ASC First Projectsall

Coordinate/update lab schedule

10 minAny other business  

Action items

  • Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster