Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minStatusAll
  • Status ASC electrical, rebar scan, anchoring
  • Status JF 4M effort
  • Status RIXS-CCD test planning
    • Masks not here yet, checking with Sallie.
    • Ground issues resolved from first test?
    • Late March slips to mid-April??
    • Do first test at SSRL to decouple from ASC sked??
  • MEC EMP testing CSPAD/ePix Date TBD
  • PH gone first week April
  • KN Wave8 upgrade for FIM CDR one fine day
  • ePix10k requires new MPODS, working issue
  • Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
  • eGun interlock doc (2wk.)
  • Lost cabinets were not delivered....(2wks)
  • KZ: ASC metro technicians are tied up. Scanning today.
  • Sean and Gibson are scanning. Hole patterns to be marked Wednesday. Drilling/Anchors Th/Fri.
  • Working with LeRoy
  • Status documentation/procedures effort
  • How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 minASC Budget UpdatemmckASC Lab Costs + Commits: $191k (75% spent)
15 minReview ASC First Projectsall

Coordinate/update lab schedule

10 minAny other business  

Action items

  •