Magnets |
[ PCD SML/ROD |
http://ped.slac.stanford.edu:8080/pem/index.php ] |
Item |
Priority |
Start Date |
Duration |
Area |
Contact |
Description |
1 |
|
14-Apr |
2-day |
PEPII |
PCD |
Remove ps from pepii for use in bc2 magnet string bx22-bx24. Remove mcor's from pepii for undulator and bsy b136 magnets. |
2 |
|
14-Apr |
2-weeks |
BSY |
PCD and K. Luchini |
Checkout BSY/LTU0 Magnet Ps and Controls. Racks in b005 |
3 |
1 |
|
2-day shifts |
LI24 housing |
PCD |
Replace bc2 magnet bx22-bx24 ps with ps from pepii |
4 |
|
?? |
10-11am |
1hr |
Kristi Luchini |
Change some CB00 to CA11 units, BSY Magnets in b136. Need slc dbInstall. |
5 |
|
14-Apr |
2-weeks |
BSY |
PCD and K. Luchini |
Test calibration |
6 |
|
14-Apr |
2-weeks |
|
PCD and K. Luchini |
Chg mini-standardize proceedure to occur if mini-stdz enabled only. Check stdzok when perturbing and clear if moving in direction opposite to stdz |
7 |
|
|
|
|
K. Luchini and J. Dusatko |
Repalce sector 20 into vsams with hytec adc's. Determine if noise levels seen earlier on some channels last month with hytec adc's is ok, or if data filtering will need to be imporved to diminish the noise level further. |
8 |
|
|
|
|
K. Luchini & PCD |
Pre-installation checkout in b24 racks for b911,b912,b913,b921. |
9 |
|
|
|
|
J. Hugyik & K. Luchini |
Replace cat6 cables in racks lkg01 to lkg06 (s20) |
10 |
|
|
|
|
PCD |
Protect power conductors on their transition thru the magnet covers |
11 |
|
|
|
|
PCD |
Investigate V-gain limitation on Q24601 PS |
12 |
|
|
|
|
PCD |
Check all connections to magnets in linac and bsy (See pcd sml/rod) |