LCLS Downtime Job List for Controls - April 10 thru 25, 2008

ROD

References

 

Date

Time

Start

April 10, 2008

8:00am

End

April 25, 2008

5:00pm

Power Outage

April 26-27th

6:00pm

Turn Back On

April 28

7:00am

Scheduled For this Week

April 28, 2008 Thru May 3 2008

Day

Time

Duration

Description

Monday

Beam Off - Injector Vault Access

 

8:00am

3+hrs

Align Laser, cathode camera

 

Beam On

 

12:00am

 

Re-calibrate rf & Get x-band on

 

Owl Shift

 

Cathode Study

Tuesday

Beam On

 

 

 

Re-evaluate, either push beam down or continue cathode study

Wednesday

Beam Off - Injector Vault Access

 

8:00am

 

Replace laser transport window

 

 

6hrs

Software Test Day - Release sw changes made during the down

 

Turn Beam On

 

2:00pm

Software Released During the Down

Item

Area

Subsystem

Contact

Description

1

Linac

Wire Scanners

Arturo Alarcon

Gear reducing software

2

LI28,LI29,BSY

Bpms

Soyna Hoobler

16 new ioc's (5 of these slc-aware). Slc-aware disabled and associated micro from scp disabled.

3

 

Slc Database

Nancy Spencer

dbInstall, new slc-aware iocs,dgrps installed,

4

 

Proxy

Nancy Spencer

Release proxy server

5

 

Laser

Matt Boyes

Controls for two new motors that control the new compressor. The changes are in IOC ioc-lr20-ls01.

Scheduled Work

BPMs

Item

Start Date

Duration

Area

Contact

Description

1

10-Apr

2.5 weeks

Linac,BSY

Sonya

Upgrade BPMs to EPICS: 9 BPMs total, in Sec 27, Sec 28, and north Arc (B136)

SLC Database

Item

Start Date

Duration

Area

Contact

Description

1

14-Apr

1hr

 

 

Db install, checkout new slc-aware micros for bpm's and magnets, checkout additions to proxy px00.

Laser

Item

Start Date

Duration

Area

Contact

Description

1

 

 

 

 

Install UPS in injector vault, which protects newport motors

LLRF(items 1-4 postponed from 4/2/8 software day)

Item

Start Date

Duration

Area

Contact

Description

1

10-Apr

1 -day

LCLS Injector, Li21 and Li24

Dayle

upgrade PACs to Pac-R3-0-0

2

10-Apr

1 -day

LCLS Injector, Li21 and Li24

Dayle

upgrade VMEs to Llrf-R5-0-8 for PCAV1 and 2 changes

3

10-Apr

1 -day

Li24

Dayle

load L3 templates on S24 VME

4

10-Apr

1 -day

LCLS Injector, Li21 and Li24

Dayle

upgrade VMEs to use event-2-6-2

5

11-Apr

2.5 -weeks

LCLS Injector, Li21 and Li24

Dayle

Test 2nd ethernet communication via private network

6

17-Apr

1 -day

LCLS Injector

Dayle

Add/test new logic to step MDL PAC incrementally to new desired phase

Magnets

[ PCD SML/ROD

http://ped.slac.stanford.edu:8080/pem/index.php ]

Item

Priority

Start Date

Duration

Area

Contact

Description

1

 

14-Apr

2-day

PEPII

PCD

Remove ps from pepii for use in bc2 magnet string bx22-bx24. Remove mcor's from pepii for undulator and bsy b136 magnets.

2

 

14-Apr

2-weeks

BSY

PCD and K. Luchini

Checkout BSY/LTU0 Magnet Ps and Controls. Racks in b005

3

1

 

2-day shifts

LI24 housing

PCD

Replace bc2 magnet bx22-bx24 ps with ps from pepii

4

 

??

10-11am

1hr

Kristi Luchini

Change some CB00 to CA11 units, BSY Magnets in b136. Need slc dbInstall.

5

 

14-Apr

2-weeks

BSY

PCD and K. Luchini

Test calibration

6

 

14-Apr

2-weeks

 

PCD and K. Luchini

Chg mini-standardize proceedure to occur if mini-stdz enabled only. Check stdzok when perturbing and clear if moving in direction opposite to stdz

7

 

 

 

 

K. Luchini and J. Dusatko

Repalce sector 20 into vsams with hytec adc's. Determine if noise levels seen earlier on some channels last month with hytec adc's is ok, or if data filtering will need to be imporved to diminish the noise level further.

8

 

 

 

 

K. Luchini & PCD

Pre-installation checkout in b24 racks for b911,b912,b913,b921.

9

 

 

 

 

J. Hugyik & K. Luchini

Replace cat6 cables in racks lkg01 to lkg06 (s20)

10

 

 

 

 

PCD

Protect power conductors on their transition thru the magnet covers

11

 

 

 

 

PCD

Investigate V-gain limitation on Q24601 PS

12

 

 

 

 

PCD

Check all connections to magnets in linac and bsy (See pcd sml/rod)

Network

Item

Start Date

Duration

Area

Contact

Description

1

14-Apr

2-weeks

LCLS & MCC Networks

T. Lahey

MCC AIP: replace SWH-MCC1 & SWH-MCC2 with new switches

2

14-Apr

2-weeks

LCLS & MCC Networks

T. Lahey

MCC AIP: complete installation of cat6 patch panel in control room and computer room

Timing

Item

Start Date

Duration

Area

Contact

Description

1

 

 

 

J. Dusatko

Swap bpm evr in sector 24 and 25

2

 

 

 

J. Dusatko

Replace FODU kf24-7a

Wire Scanners

Item

Start Date

Duration

Area

Contact

Description

1

 

 

 

 

Gear reducer added to some wire scanners. Test.

2

 

 

 

 

Updated save/restore of pmt hv on pv.