Procedure for use (alignment, operation)


~8/2 Thursday: documentation, pictures,...

8/3 Friday: iAT testing day

8/5 Monday: iAT work morning, Eric measures stuff in the afternoon

8/6 Tuesday: removal of SPL/LPL swap in the morning, ePix10ks IN and waterline connection in the afternoon (Ariel)

8/7 Wednesday: cabling of motors and DAQ (Peregrine)

8/8 Thursday: shot and EMP test (Eric, Philip H, DK, HJL)

8/9 Friday: shot and EMP test (Eric, Philip H, DK, HJL)

8/12 Monday: disconnect lines....removal of LPL/SPL setup in the afternoon (Ariel)

8/13 Tuesday: Users come

8/29 Thusday: Commissioning