Some notes on tasks to tackle before sending the full power beam into the tunnel.

Also some ideas on first tests for when we ramp up the laser.


Before full power operation


During ramp up


  • Attenuate laser and gradually ramp up
  • Check light levels on all cameras, look out for abnormalities that indicate damage
  • Check vacuum levels as beam is dumped on compressor block
  • Check vacuum levels as beam is dumped on laser beam dump in PB
  • Check for damage, signs of ablation etc. around compressor block and laser beam dump in PB
  • Check if scaling on laser diagnostics matches expected energy scaling (for on-shot energy measurement)


After initial ramp up

  • Check optics and cameras for damage


Full power checklist


  • Laser aligned upstairs, through transport and to diagnostics
  • Check cameras for beam clips
  • Motors in safe positions
  • If probe only work, insert compressor beam block
  • Laser flippers for filtering in, confirm on cameras, check for any clips
  • Block laser
  • Block CW diode
  • Attenuate laser
  • Remove RP attenuator 
  • Unblock laser
  • Slowly ramp up while observing cameras and vacuum levels
  • Full power! 