Prepare
- Verify power off. (MPOD panel or IoC panel)
- Install detector in Marietta.
- Connect chiller, start flow.
- Connect data fiber.
- Connect gas line if applicable, start flow at 5l/m.
Power
- Set known values on mpod.
- Pin out cable according to diagram.
- Turn off mpod.
- Connect power cable to detector.
- Set operating voltages on mpod.
- Start DAQ and configure to begin idle.
Stabilize for 15 minutes
- For 10k: Wait for temperature < 10C and humidity < 10% (ideally under 5%)
Record Voltage/Current/Temperature Values
Measure Pedestals (run charge injection script)
Collect Fluorescence Data
- Make sure centers line up (detector and target)
- Take pedestals if you haven't already
- Silver: ~10cm distance, 35kVp, 45uA (50 was old current, proved to be too high, saw burn-in)
Direct Illumination w/Mini-X
Process Data
Update Traveller