Set and status planning activities for detector development and deployment.
Discussion items
Time
Item
Who
Notes
30 min
Status
All
ePix Update:
Kickoff meeting for ePix fab April 9, 3pm, Kite
Testing to begin on ePixHR soon.
Peter Denes visited last week to discuss SXR imager requirements:
Notes from last SXR requirements discussion now posted here. Latest version in circulation for review, need to finalize a the end of this week (April 12)
TES re-baseline document has been reviewed by NIST/CU and some comments have been incorporated. Next step is to forward to LCLS management for approval.
Costed proposal from Anton for MCP/TImepix tests has been formulated as a PEC briefing...turns out that it doesn't need PEC, so will re-cast as a 'project charter' this week and turn on the funding. Would like to arrange a kickoff meeting, perhaps a road trip to UCB/SSL?
Update > Status RIXS-CCD test planning
Masks here, holder ready
tests last week reached 300Hz operation, not sure of effect on performance.
Status:
MEC EMP testing CSPAD/ePix Date TBD
KN Wave8 upgrade for FIM CDR Mid-April
ePix10k requires new MPODS, working issue
Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
eGun interlock doc (2wk.)
Lost cabinets were not delivered....(2wks)Now set for refund and re-order as two rolling tool chests
KZ: Control room furniture install this afternoon.Furniture installed, wall cabinets remain to go.
Status documentation/procedures effort
How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 min
Budget Update
mmck
ASC: $255k spent, $3k remains
Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 min
Review ASC First Projects
all
Coordinate/update lab schedule
10 min
Any other business
Action items
Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster