Technical Path to DR and OPA Reviews
Date | Task | Links | Experimental Systems | Laser Systems | Conventional Facilities | Controls Systems |
---|---|---|---|---|---|---|
Worry List ("Deliverability Challenges" from Flat Funding Profile) |
|
|
|
| ||
Content for Supporting Documentation: Recommendations | Recommendations: |
|
|
|
| |
Content for Supporting Documentation: Documents |
|
|
|
| ||
Content for Supporting Documentation: Risks |
|
|
|
| ||
8/31-9/25 | Speakers Prepare Plenary and Breakout Presentations - Technical Content |
|
|
|
| |
9/26-9/27 | Insert Cost and Schedule Charts into DR presentations |
|
|
|
| |
9/27-9/28 | Director's Review slide lay down (Internal - Plenaries ) |
|
|
|
| |
10/2-10/6 | Director's Review slide lay down (Internal - Breakouts) |
|
|
|
| |
10/12-10/13 | Director's Review dry run (Internal, Plenaries and Breakouts, 2-day hybrid "open house") |
|
|
|
|
References: WBS Dictionary