Item/Task | sub-item/task | Dates | Comment |
---|---|---|---|
FEB | |||
layout | Done 8/4 | ||
fabrication | 8/6-8/12 | ||
loading | 8/13-8/20 | ||
testing | 8/21- | ||
L4-6 Half-module production | |||
apv25 loading | 8/7 | ||
hybrid & sensor QA | 8/12 | ||
half-module production incl. QA | 8/19-8/29 | When Tim is back. | |
L1-3 Module assembly | |||
5. Module assembly L1-3 6. Module assembly L4-6 7. Survey--modules, u-channels, overall overview and procedures needed 8. Mech assembly dry run 9. Motion control system check 10. inner cables-- layout, assembly, and test 11. meazzanine boards--layout, fab, load, test 12. target--design, fab, check 13. wires--design, fab, check 14. flange cards 15. outer power cables 16. Chiller and cooling system checkout 17. PS checkout 18. Shipping boxes