You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 8 Next »

Do edits and updates to the diagram on o365 teams

Also see a simplified version of the diagram.

  • Here is the following fiber inventory for the buildings in question 

    B050 to B005, room 112 - 144 strand SM, 36 unterminated (available)

    B005 to B950, room 203 - 144 strand SM, 36 unterminated (available)

    B050 to B901, room 121 - 24 strand SM, all terminated, 12 used 12 available

    B050 to SRCF IT closet - 144 strand SM, all terminated, 34 used 110 available

    P.S.

    B050, B005, B921 are all hubs where there is fiber available to go in various directions. B921 will connect to B901 and we have 2 each 72 strand SM cables there, one is terminated and 26 strands are used up. The other 72 strand cable we will have to pull in additional cable runs from B209 to B005 to complete this run and make it available

Or use this older copy: ir4-dc.pptx Map of fibre paths from 9/2016.  This copy is no longer current or being updated.  Use the O365 teams copy above.

  • No labels