LSSTCAM charge numbers:16714-B2121, 10139-B2019
Other upcoming tasks/issues coordinated with Nadine Kurita for LSST Camera can be found here Camera Documentation Planning.
Deliverable | Complete Date | Responsible | Blockers/Issues |
---|---|---|---|
eTraveler standards, conventions, best practices documentation. All Camera subsystems must use. | 4/20/15 | Mark/Robert |
|
eTraveler procedure authoring for raft electronics boards | ??? | Robert |
|
Deliverable | Complete Date | Responsible | Blockers/Issues |
---|---|---|---|
With Walt Innes, plan assembly sequence and eTraveler procedure authoring for ~500 commercial parts | 5/15 | Robert | |
Plan for Camera operations & maintenance documentation, relationship to eTraveler | 7/15 | Mark/Robert |
|
Deliverable | Complete Date | Responsible |
---|---|---|
3 monthly reports | Monthly 15th, 31st | Robert |
Camera subsystem FDR, MRR site and document prep | Roughly monthly | Mark |
Camera document control: doc prep, routing, release | (As needed) | Mark |
Charge numbers:13877-T2101
Deliverable | Complete Date | Responsible | Blockers/Issues |
---|---|---|---|
Finish release of 0266 ICD | 4/20 | Mark |
|
Finish release of Platform ICD | 4/20 | Mark |
|
Finish release of HPS FRSs | 4/27 | Mark |
|
Finish release of HPS ESDs | 5/11 | Mark |
|
Charge numbers:
Deliverable | Complete Date | Responsible |
---|---|---|
ePix100A detector data sheet | Arndt | |
ePix100A installation guide | Arndt | |
ePix100A detector ops/api guide | Arndt |