JIRA Items

LSSTCAM

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Other Items

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

LSST Camera (1.8 FTE)

LSSTCAM charge numbers:16714-B2121, 16713-B2311

Other upcoming tasks/issues coordinated with Nadine Kurita for LSST Camera can be found here Camera Documentation Planning.

Short term projects/deliverables

DeliverableComplete DateResponsibleBlockers/Issues
Write eTraveler assembly and test procedures for Camera Cryostat including refrigeration system.11/30/16Mark/Robert 
eTraveler standards, conventions,
best practices documentation. All Camera
subsystems must use
5/16/16Mark/Robert
  • Standards complete, project to announce and socialize.
Write eTraveler procedures for CR wavefront sensor receipt, verification and shipment to SLAC6/10/16Mark

Input from Camera QA

eTraveler procedure for mechanical
assembly of raft electronics boards
(attach coldbars and FPGA heat sink)

Done 5/4/16

Robert 
eTraveler procedure for raft electronics
board initial testing (bring up board and
load firmware. Prep for TS-REB testing)

Complete 5/23

Robert 
Meet with Camera on what RGA snapshots to post for REB boards5/26Mark 
eTraveler procedure for posting RGA
results
Complete TBDMark/Robert

Coordination with Mark Bostic at SLAC for posting RGA
results

Medium/long term projects/deliverables

DeliverableComplete DateResponsibleBlockers/Issues
Write demo eTraveler procedures to show Walt Innes
how eTraveler can be used to monitor and control
auxiliary electronics inventory
Done 4/20/16Robert 
With Walt Innes, plan assembly sequence
and eTraveler procedures for ~500
commercial auxiliary electronics parts

Complete TBD
(Ongoing)

Robert 
Write eTraveler procedures for inventory control
of commercial auxiliary electronics parts
6/15Mark/Robert 
Write eTraveler procedures for testing of auxiliary
electronics assemblies as needed (e.g. Camera
protection system)

Complete TBD

Robert 
Consult with SLAC Camera subsystems (Cryo, CBM,
Shutter, I&T) on assembly sequences, scope and "load balancing"
for writing eTraveler procedures
6/15Mark/Robert 
Plan for Camera operations & maintenance
documentation, relationship to eTraveler
7/15Mark/Robert
  • Project decision on how suitable eT is
    for operations and maintenance

Recurring projects/deliverables

DeliverableComplete DateResponsible
3 monthly reportsMonthly 15th, 31stRobert
Camera subsystem FDR, MRR site and document prepRoughly monthlyMark
Camera document control:
doc mgmt, prep, routing, release
(As needed, currently
4-10 hours per week)
Mark

LCLS-II, LCLS (0.1 FTE)

Charge numbers:13877-T2101

Short term projects/deliverables

DeliverableComplete DateResponsibleBlockers/Issues
Finish release of 0266 ICD4/27Mark
  • Out for signoff (still)
Finish release of Platform ICD4/20Mark 
Finish release of Timing ICD5/4Mark
  • Talk to Matt Weaver and Boyes on some scope still
    floating around
Finish release of HPS FRSs5/11Mark
  • Waiting for direction from E-beam Controls
Finish release of HPS ESDs5/11Mark
  • Waiting for direction from E-beam Controls

ePix (0.1 FTE)

Charge numbers:

Medium/long term projects/deliverables

DeliverableComplete DateResponsibleBlockers/issues
Develop ePix100 "advanced user" doc
for LCLS-II: full register documentation of readout
system and ASICs; describe known detector
edge cases behavior and configurations
TBDMark 
ePix100A detector data sheet5/13Mark
  • Done, needs only proofread before sending out
ePix100A installation guide5/13Mark
  • Done, needs only proofread before sending out
ePix100A detector ops/api guide5/13Mark
  • Waiting for some sections from Gabriel on calibration use cases

TID-AIR General Work (??? FTE)

Most of these are wish listy items with no time or budget.

Medium/long term projects/deliverables

DeliverableComplete DateResponsibleBlockers/issues
Summer intern - AIR Elx software library API docs, consider Doxygen   
Review permissions scheme for ppareg
Confluence space
 Mark 
Reorg and new navigation scheme for
ppareg Confluence spaec
 Mark 
Run interference with LCLS, LCLS-II doc
control and CDR/PDR/FDR and CD* review
prep.
 Mark 
  • No labels