Webex meeting for those not at SLAC: https://confluence.slac.stanford.edu/display/hpsg/Webex+connection+details
Status
- Signal flange boards
- One flange ready to go
- Ordered spare boards today. Five day turn but needs to be sent out for loading.
- Expect to have in hand tested 9/23.
- Front end boards
- Noise tests show improved performance compared to previous versions. Noise level around 55ADC.Sho or Omar will send around first results.
- Next week Omar/Sho/Pelle will setup and start doing multiple tests to stress the board.
- Second board is finished loading today.
- We have started loading the there 8 boards. Will be ready end of next week most likely.
- We have decided to order 5 more for spares today.
- Mezzanine cards
- LV power board ordered, should be here By Wed next week. Needs connector loading ~1-2 days.
- HV power board done and in hand.
- FEB card ordered, should be here By Wed next week. Needs connector loading ~1-2 days.
- Hybrid card ordered, should be here By Wed next week. Needs connector loading ~1-2 days.
- Tung is still working on the cross-over board layout
- RTM status
- Ryan discovered another problem with the new revision. Tung has got the fix on the top of his list and should be done by Mon. Have to get a 3 day turn on it.
- We can use the devboard to commission up to two front-end boards with the RCE platform. Most likely this will not hold us up but we'll keep an eye on it.
- Cabling
- Power draw of new FEB verified: redoing all cables and breakout boxes (not clear when ready)
- 3rd and last HV long cable is being produced now (done early next week).