Webex meeting for those not at SLAC: https://confluence.slac.stanford.edu/display/hpsg/Webex+connection+details

 

Status

  • Signal flange boards
    • One flange ready to go
    • Ordered spare boards today. Five day turn but needs to be sent out for loading. 
    • Expect to have in hand tested 9/23.
  • Front end boards
    • Noise tests show improved performance compared to previous versions. Noise level around 55ADC.Sho or Omar will send around first results.
    • Next week Omar/Sho/Pelle will setup and start doing multiple tests to stress the board.
    • Second board is finished loading today.
    • We have started loading the there 8 boards. Will be ready end of next week most likely.
    • We have decided to order 5 more for spares today.
  • Mezzanine cards
    • LV power board ordered, should be here By Wed next week. Needs connector loading ~1-2 days. 
    • HV power board done and in hand. 
    • FEB  card ordered, should be here By Wed next week. Needs connector loading ~1-2 days. 
    • Hybrid card ordered, should be here By Wed next week. Needs connector loading ~1-2 days. 
    • Tung is still working on the cross-over board layout
  • RTM status
    • Ryan discovered another problem with the new revision. Tung has got the fix on the top of his list and should be done by Mon. Have to get a 3 day turn on it. 
    • We can use the devboard to commission up to two front-end boards with the RCE platform. Most likely this will not hold us up but we'll keep an eye on it. 
  • Cabling
    • Power draw of new FEB verified: redoing all cables and breakout boxes (not clear when ready)
    • 3rd and last HV long cable is being produced now (done early next week).  