30 min | Priorities Review | All | - 2021 events:
- Projects new starts:
- ePixM project plan submitted, baselined in P6.
- SparkPix-S Phase II (full-size ASIC for sparsification engine), on-track
- ePixHR V: mounted for test next week.
- TXI Detectors (2Mp and 140kp based on ePixHR @5kHz) Wafer purchase order placed, delay to delivery of about 3 months, other things likely to slip as well.
- ePixUHR (130nm TSV structure to reach 100kHz), CDR completed, PEC approved start, project underway.
- Production:
- spare modules (0.5 & 1mm) Module order in work, new sensor order delayed. No-ghost received.
- Approved 3d copy of ePix10k2m: underway, November delivery (may slip due to module delay)
- Approved spare quads for MEC: underway, August delivery(?)....will slip, working on updated delivery date.
- Proposed in-air 2m/1mm project plan submitted to OIP.
- Proposed UED detector upgrade, planning in work.
- Proposed ePix10k4m (concept)
- RIXS-CCD/cooler test and verification: Acceptance tests show vibe spec met (long settling time). Working on triggering. NEH folks have been updated.
- HiZ collaboration tests: Ge and CZT modules have been tested in lab, LCLS beam times secured, Boo working bracket fab.
- Outreach for R&D support (SparkPix-ED, SparkPix Delta).
- SBIR effort for UXI not funded.
- Group priorities review:
- Testing
- Run 'standard' cal on two 10k smalls with new firmware, log tracker.
- CompEnOn study during CXI checkout time? 111, 1a vs 19?
- Any ePix100 detectors in ASC? Can we figure out what's wrong with ePix100/7?
- RIXS-CCD cooler test planning.
- Analysis
- Gather and process relevant commissioning data for Mp travellers on Confluence.
- Solid pedestals
- Noise map
- Response uniformity (mini-X cu-fluorescence)
- Bootstrap gain (sealed source)
- Linearity (signal injection)
- Documentation
- Complete on-line travellers for Mp detectors
- Development
- Lab 'commissioning'
- DAQ
- Storage nodes configured, put in use?
- LCLS I/II compatibility?
- Chase racks anchored....cables, water status?
- Vac chamber for in-lab tests? Compatible with XPP alcove?
Actions:
|
30 min | Status |
| LDAC preps dominate. Website is up, needs populating Cal team meeting needs reschedule. LDAC Panel assembled, agenda mostly settled, working on the panel charge this week. Year-end spending needs?? Running out of time.
KN: - No timing in ASC...probably due to power issues in NEH.
- Rayonix shipped.
- Hunting for ePix small vac hardware....some parts missing.
PH: - ePix10k switching issues.....noise much higher in FoLo.
- Working w/B to improve pedestals, sharing data with Gabriel.
- UXI IH put in for Run20....could let us offer UXI for user experiments??
CH: - Got ePix assembly bracket...can try to run zombie masking ASICs looking for configurable mode.
- CZT guy is back from vacation....will try to have him fix contact.
- No word from Stephen Boo...need update.
- Starting linearity characterization using MFX data.
RA: - Prepare for mid-july RIXS-CCD
- Lost Derek, may need May Ling to help training on laser vibrometer
- Need mtg for acceptance test planning (Friday)
BN: - Looking at FoLo data, still tryng to parse/understand
- Went through fluorescence process.
- Min/max stitching.
- Run cal on new ePix firmware.
- Grafana setup to alert Slack channel.
- Made updates to detector website, in work.
- Working with PH on porting PyRoot to Python.
CK: - Setting up vac components for RIXS-CCD.
- Trying to get cables complete for CSPD/CXI
- Trying to move water/power effort in chase.
|