Attendees
Goals
- Set and status planning activities for detector development and deployment.
Discussion items
Time | Item | Who | Notes |
---|
10 min | Beamtime support update |
|
|
30 min | Priorities Review | All | - 2021-2 events:
- Projects new starts:
- ePixM project plan submitted, baselined in P6. Mech design review held Jan 24 (actions circulated). Received sensor wafers from L-Foundry, dicing.
- SparkPix-S Phase II (full-size ASIC for sparsification engine), on-track. Budget request for MBES application.
- ePixHR V: beamline test completed, data analysis slow.
- TXI Detectors (2Mp and 140kp based on ePixHR @5kHz) CO2 cooling selected, Bora cooler on oreer (ASC??)Wafer purchase order placed, delay to delivery of about 3 months, other things likely to slip as well.
- ePixUHR (130nm TSV structure to reach 100kHz), CDR completed, PEC approved start, project underway.
- Production:
- spare ePix10k modules (0.5 & 1mm) First batch of no-ghost received, now packaging and wirebonding.
- Approved 3d copy of ePix10k2m: underway, March delivery (slipped due to module delay, PCB issues)
- Approved spare quads for MEC: delivered, in test.
- Proposed in-air 2m/1mm project plan submitted to OIP.
- Proposed UED detector upgrade, planning in work.
- Proposed ePix10k4m (concept)
- RIXS-CCD/cooler test and verification: Available for PCDS testing. Working on test report, and review with NEH2.2.
- HiZ collaboration tests: Data analysis in work (plan?). Follow-on proposal needed.
- Outreach for R&D support (SparkPix-ED, SparkPix Delta).
- SBIR effort for UXI not funded.
- Group priorities review:
- Testing
- Develop workable version of 'standard' cal script, test on 10k small, Bhavna: Possible to demonstrate by week of Feb 14?
- Air-scatter CompEnOn study to refine timing...Philip/Bhavna, possible to complete analysis by week of 2/14?.
- Acceptance test new quads Bhavna, possible to complete basic cal (pedestals, charge-injection) floe by week of 2/14?
- Documentation
- Complete on-line travellers for Mp detectors
- Development
- Hi-Z test data analysis (Conny, is there a reasonable target for week of 2/14?
- Testing ePixHR in our lab: Conny, is it possible/worthwhile/important enough to try to get it running in our lab by week of 2/14??
- Lab 'commissioning'
- DAQ
- Get water and power completed in mech chase (reasonable milestone by 2/14?)
- Marietta interlocks for Kimball. Need to check with Jenna
- Marietta fixturing for calibration of epix, JF smalls
- Vac chamber for in-lab tests? Compatible with XPP alcove? Chris/az/Philip/Cony confer and select config by 2/14??
Actions:
|
30 min | Status |
| No update on dept head recruiting. Taking vacation time on Fridays. Thanks for help in lab cleanup. Better, need more work and mach room completion. RA boxes?? Complete tests on RIXS-CCD this week and store safely - fit check looks OK, need more cables...asked Gerogi for PA code. Chiller issues in UED not reproducible in lab.....compare pressure readings? Opportunity to focus on lagging priorities: Marietta/Kimball, water/power, RIXS-CCD data analysis/reporting, beamtime data analysis, vac test chamber? Status on water/power?? Topics for Cal team meeting? Bojan to join going forward.
KN: - No timing in ASC...probably due to power issues in NEH.
- Rayonix shipped.
- Hunting for ePix small vac hardware....some parts missing.
PH: - Getting ready for UXI test...no GaAs available unfortunately
#CH: - Christmas tree setup for Ge
- Flex cable may be too short....will check today.
- HR camera back to TID.
- Boards being modified for HV CZT
- NYC 10/14-20.
#RA: - Need mtg for acceptance test planning (Friday)
BN: - Looking at FoLo data, still tryng to parse/understand
- Went through fluorescence process.
- Min/max stitching.
- Run cal on new ePix firmware.
- Grafana setup to alert Slack channel.
- Made updates to detector website, in work.
- Working with PH on porting PyRoot to Python.
CK: - Setting up vac components for RIXS-CCD.
- Trying to get cables complete for CSPD/CXI
- Trying to move water/power effort in chase.
|
5 min | Budget Update | mmck | - M&S Status (Through July)
- Labor snapshot (July actuals):
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule. |
10 min | Any other business |
|
|
Action items: