Current Plan for April Start-up

  • April 1st - begin 2 weeks of PPS
  • April 19th - beam on
  • April 19 through May 5 - beam tune-up
  • May 6 - Users start

Possible Alternate Plan

  • April 19th through September(question) no 120Hz user experiments
  • April 19th through September User experiments at 30Hz
  • April 19th through September testing at 120Hz through TD11 only