FACET-II MD Template (Word)

2024 MD Planning  & Priorities

PriorityMD ItemProcedure Link

Machine Time

(shifts)

Responsible

Party

Needed ByPrerequisitesNotesComplete
3Injector setup for 10deg off Schottky zero crossing
3White
TCAV0 operationalMaybe investigate smaller laser spot
3Laser spot size variation



Discussion with Glen...

3Linac Ballistic Data
5




3S20 Ballistic Data



Good pencil beam config

3Individual mechanical<>magnetic offsets in L2

Loney



110-2 peak power 
1

Kalsi, Loney

ASAP
Move peak power detection from WVG FWD to cavity probe
1S20 BBA
2

Yocky





2-4Notch Collimator recommissioning
1+2


Current energy spread may not be compatible with clean cuts
2S20 matching studies/emittance in S20

S20 Emittance and Matching

1White
Good pencil beam config,
S20 Quad BBA,
S20 launch feedback


32nC running/instability investigation
2Loney

FJD interested
1Two-bunch prep/setup
8Yocky*Early 2024


4

BLEN sensitivities

BLEN Sensitivities MD
Alsberg



2

S20 BLEN



Kalsi



2Investigate orbit dependent matching into L2

White*
BBA, working steering appFJD notes similar issue in LCLS–likely eta from BC1
1Complete ORM
Loney
Analysis tools 
Done?
2Tuning IP with smaller beta*

Yocky



1Pencil beam configOct 13, 2022
Alsberg



3Learning data for MDL FF / Track hardware issuesOct 6, 2022
Alsberg



4RF kicks

Alsberg 



4Linac BBA (rechecks)BBA Shift Plan
Loney



3Toroid ringing investigationSep 1, 2022
Alsberg



4Injector RF Standby triggering

Loney



2Automated Steering development

Buschmann(?)
good R measurements and ability
to implement those into steering app


2L1 orbit stability studyOct 6, 2022
Parker



2RF stability (jitter, jumps, and djrift)Sep 15, 2022
Ripman



3PCAV 0 commissioning 
2Loney
Thing works 

2TCAV3 commissioning
2

Thing works 

2DC magnet stabilitySep 29, 2022
Parker



2TCAV0 study (sigz v. Sch. phase, etc.)Oct 6, 2022 TCAV0 Shift Plan
Parker


Done?
1Linac wakefield bump tuning exploration

Yocky



1Laser heater TTO






2New Phase scan GUI checkout/deployment
~0.5Buschmann
Stable beam to S20GUI ready to test with beam
3New phase scan GUI L0 (10-3,4) automation
~0.5Buschmann
Stable beam to TD11Code still to-be-written

Software development/testing







Past Completed MD Programs 

MD ItemProcedure Link

Machine Time

(shifts)

Responsible

Party

PrerequisitesNotesCompleted
S20 BBAOct 13, 20222

Yocky



x
S20 matching studies/emittance in S20

Sep 29, 2022

<link>

1WhiteGood pencil beam config,
S20 Quad BBA,
S20 launch feedback

x
2nC running/instability investigation
2Loney
FJD interestedx
Pencil beam configOct 13, 2022
Alsberg

x
Learning data for MDL FF / Track hardware issuesOct 6, 2022
Alsberg

?
Linac BBABBA Shift Plan
Loney

x
Toroid ringing investigationSep 1, 2022
Alsberg

?
DC magnet stabilitySep 29, 2022
Parker

x
Linac wakefield bump tuning exploration

Yocky

?
Commissioning Laser Heater 

Yocky*
Laser Heater Commissioning Task Listx
7-hole Cathode Alignment Procedure <1Loney

x


Link to FACET-II Global Planning Airtable 

Link to FACET-II PAMM Planning Airtable