This page attempts to block out the noticeable episodes of computing and their priority and need for resource availability.
Instrument Related - Pre Launch
What |
When |
Resource Uptime Needed |
---|---|---|
vibe/acoustic |
|
|
TVAC |
Aug-Sept (40 days) |
up to 8 hr outages allowed |
Kennedy Ops |
|
|
Flight Operations Post Launch
What |
When |
Resource Uptime Needed |
---|---|---|
First 2 weeks |
Feb |
"Guaranteed" up |
Next 6 weeks |
Through to end March |
|
Routine Ops |
April onwards |
up to 8 hrs; max 48 hrs |
Simulations
What |
When |
Resource Uptime Needed |
---|---|---|
Preparations for 1 year run |
Several bursts of 1-3 farm-days, July-Aug |
Advance notice for up to a few days' outage |
Backgrounds for 1 year run |
3 weeks in Sept |
Advance notice for < 1 day outage |
1 year run |
3 weeks in Oct |
Advance notice for < 1 day outage |
ISOC test datasets |
More bursts of 1-3 farm days, July-Sept |
Advance notice for up to a few days' outage |
Post ISOC test/pre launch datasets |
end Oct - Jan |
Advance notice for up to a few days' outage |
|
|
|
|
|
|