These are the instructions from FACETHOME → Experiment/LI20 → PAMM:

  1. Keep up with documentation in eLog.
  2. Take photos to document new installations or changes.
  3. Pump down . . .
  4. Take a document position/focus of each Profile Monitor and send to eLog.
  5. Check MPS and EPS permits.
  6. Check that everything is extracted from beamline.
  7. Check vacuum.
  8. Update camera calibrations and ladder positions.
  9. Take trash to top of stairs (keep metal/non-metal separate).
  10. Make sure aisle is clear. Move carts to alcove under the stairs.
  11. Leave items for survey on shelf at top of stairs.

Management

  • Email PAMM summary to FACET management and users.
  • Close CATERs.