The following supply list and step by step guide will vary based on individual BIO specs and serves only as a general guideline.

General Supply List

  • Drilling tools
  • Anchors
  • Anchor expoxy (check BIO but standard is hilti epoxy)
  • aluminum siding
  • aluminum tape
  • gray caulk (to match flooring)
  • set screws (adjust height of plate)
  • Grout (epoxy100 EPOXY GROUT 22# KIT 493014 standard or cement pending on (question))
  • painters tape/newspaper (to cover up plate from grout)
  • nylon bolts/threaded rod (the size of anchors to insert into mounts to prevent grout from getting in)

Step-by-step guide

  1. BIO Approval
  2. Drill anchors
  3. Epoxy anchors (typically BIO present) & let cure for time needed
  4. Move base plate into place & insert set screws
    1. Cover up ground facing holes with painters tape if necessary to prevent grout filling
  5. Call alignment to set position of plate
  6. Fabricate aluminum side plates
  7. Caulk to sides of base plate & aluminum tape corners
  8. Cover top of base plate to prevent grout spillage
  9. Mix grout
  10. Pour grout & let cure for time needed
  11. Torque down anchors (typically BIO present)
  12. Done



Individuals with the most experienced and can be referenced for knowledge are abc.