The following supply list and step by step guide will vary based on individual BIO specs and serves only as a general guideline.
General Supply List
- Drilling tools
- Anchors
- Anchor expoxy (check BIO but standard is hilti epoxy)
- aluminum siding
- aluminum tape
- gray caulk (to match flooring)
- set screws (adjust height of plate)
- Grout (epoxy100 EPOXY GROUT 22# KIT 493014 standard or cement pending on )
- painters tape/newspaper (to cover up plate from grout)
- nylon bolts/threaded rod (the size of anchors to insert into mounts to prevent grout from getting in)
Step-by-step guide
- BIO Approval
- Drill anchors
- Epoxy anchors (typically BIO present) & let cure for time needed
- Move base plate into place & insert set screws
- Cover up ground facing holes with painters tape if necessary to prevent grout filling
- Call alignment to set position of plate
- Fabricate aluminum side plates
- Caulk to sides of base plate & aluminum tape corners
- Cover top of base plate to prevent grout spillage
- Mix grout
- Pour grout & let cure for time needed
- Torque down anchors (typically BIO present)
- Done
Individuals with the most experienced and can be referenced for knowledge are abc.